Schedule metric title.jpg
(starteur-ed)Schedulemetric.PNG


Schedule Metric Score & Description

Schedulemetric(chart).PNG
Iteration Estimated no. of days Actual no. of days Metric Score Description
1 8 8 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
2 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
3 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
4 15 15 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required.
5 10 11 0.91 Our estimates are fairly accurate. Project schedule is on track. 1 buffer day used to debug Email Access Codes due to complexity in number of possible scenarios with different type of users (students)
6 12 12 1 Our estimates are fairly accurate. Project schedule is on track. No action required.
7 12 12 1 Our estimates are fairly accurate. Project schedule is on track. No action required.
8 13 14 0.93 Our estimates are fairly accurate. Project schedule is on track. No action required.
9 12 9 1.33 Iteration ended early as Batch Report module was pushed back due to client's inability to provide algorithm on time. Team decided to change schedule and Supervisor was informed of changes.
10 10
11
12
13
14