Schedule metric title.jpg
(starteur-ed)Schedulemetric.PNG


Schedule Metric Score & Description

Schedulemetric(chart).PNG
Sprint Estimated no. of days Actual no. of days Metric Score Description
1 8 8 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
2 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
3 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
4 15 15 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required.
5 10 11 1 Our estimates are fairly accurate. Project schedule is on track. Difficulty in setting up email server for Starteur and it was exams period for SMU Term 1. As such, project was delayed. 1 buffer day used.
6 12 12 1 Our estimates are fairly accurate. Project schedule is on track. No action required.
7 12 12 1 Our estimates are fairly accurate. Project schedule is on track. No action required.
8 13 13 1 Our estimates are fairly accurate. Project schedule is on track. No action required.
9 14 11 - Batch report module was pushed back due to client's inability to provide algorithm on time. Supervisor was informed of change in schedule.
10 14
11 13
12 12
13 12
14 8