IS480 Team wiki: 2015T2 Starteur Project Schedule Metrics
Revision as of 12:26, 12 January 2016 by Choryi.poon.2012 (talk | contribs) (→Schedule Metric Score & Description)
Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
---|
Schedule Metric Score & Description
Sprint | Estimated no. of days | Actual no. of days | Metric Score | Description |
---|---|---|---|---|
1 | 8 | 8 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
2 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
3 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
4 | 15 | 15 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
5 | 10 | 11 | 1 | Our estimates are fairly accurate. Project schedule is on track. Difficulty in setting up email server for Starteur and it was exams period for SMU Term 1. As such, project was delayed. 1 buffer day used. |
6 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
7 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
8 | 13 | |||
9 | 14 | |||
10 | 14 | |||
11 | 13 | |||
12 | 12 | |||
13 | 12 | |||
14 | 8 |