Difference between revisions of "IS480 Team wiki: 2015T2 Starteur Project Schedule Metrics"
Jump to navigation
Jump to search
Line 109: | Line 109: | ||
| style="text-align:center" | 8 | | style="text-align:center" | 8 | ||
| style="text-align:center" | 13 | | style="text-align:center" | 13 | ||
− | | style="text-align:center" | | + | | style="text-align:center" | 13 |
− | | style="text-align:center" | | + | | style="text-align:center" | 1 |
− | | style="text-align:center" | | + | | style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required. |
|- | |- | ||
| style="text-align:center" | 9 | | style="text-align:center" | 9 | ||
| style="text-align:center" | 14 | | style="text-align:center" | 14 | ||
− | | style="text-align:center" | | + | | style="text-align:center" | 11 |
− | | style="text-align:center" | | + | | style="text-align:center" | - |
− | | style="text-align:center" | | + | | style="text-align:center" | Batch report module was pushed back due to client's inability to provide algorithm on time. Supervisor was informed of change in schedule. |
|- | |- |
Revision as of 10:12, 7 February 2016
Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
---|
Schedule Metric Score & Description
Sprint | Estimated no. of days | Actual no. of days | Metric Score | Description |
---|---|---|---|---|
1 | 8 | 8 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
2 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
3 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
4 | 15 | 15 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
5 | 10 | 11 | 1 | Our estimates are fairly accurate. Project schedule is on track. Difficulty in setting up email server for Starteur and it was exams period for SMU Term 1. As such, project was delayed. 1 buffer day used. |
6 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
7 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
8 | 13 | 13 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
9 | 14 | 11 | - | Batch report module was pushed back due to client's inability to provide algorithm on time. Supervisor was informed of change in schedule. |
10 | 14 | |||
11 | 13 | |||
12 | 12 | |||
13 | 12 | |||
14 | 8 |