HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2015T2 Starteur Project Schedule Metrics"

From IS480
Jump to navigation Jump to search
m
Line 78: Line 78:
 
| style="text-align:center" | 1.00
 
| style="text-align:center" | 1.00
 
| style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required
 
| style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required
 +
 +
|-
 +
| style="text-align:center" | 4
 +
| style="text-align:center" | 15
 +
| style="text-align:center" | 15
 +
| style="text-align:center" | 1.00
 +
| style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required
 +
 +
|-
 +
| style="text-align:center" | 5
 +
| style="text-align:center" | 10
 +
| style="text-align:center" | 10
 +
| style="text-align:center" | 1.00
 +
| style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required
 +
 +
|-
 +
| style="text-align:center" | 6
 +
| style="text-align:center" | 11
 +
| style="text-align:center" | 13
 +
| style="text-align:center" | 0.85
 +
| style="text-align:center" | 2 Developers were called up for ICT (In-camp training) from 7 December onwards, lasting for a week. Despite efforts to mitigate the impact, development was delayed for 2 days. 2 buffer days were used.
 
<!--CONTENT END-->
 
<!--CONTENT END-->

Revision as of 14:17, 21 December 2015

Starteur.jpg

HOME

ABOUT US

PROJECT OVERVIEW

PROJECT MANAGEMENT

DOCUMENTATION

Schedule Schedule Metrics Bug Metrics Risk Management Change Management


(starteur-ed)Schedulemetric.PNG


Schedule Metric Score & Description

Schedulemetric(chart).PNG
Sprint Estimated no. of days Actual no. of days Metric Score Description
1 8 8 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
2 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
3 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
4 15 15 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
5 10 10 1.00 Our estimates are fairly accurate. Project schedule is on track. No action required
6 11 13 0.85 2 Developers were called up for ICT (In-camp training) from 7 December onwards, lasting for a week. Despite efforts to mitigate the impact, development was delayed for 2 days. 2 buffer days were used.