Line 78: | Line 78: | ||
| style="text-align:center" | 1.00 | | style="text-align:center" | 1.00 | ||
| style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required | | style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required | ||
+ | |||
+ | |- | ||
+ | | style="text-align:center" | 4 | ||
+ | | style="text-align:center" | 15 | ||
+ | | style="text-align:center" | 15 | ||
+ | | style="text-align:center" | 1.00 | ||
+ | | style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required | ||
+ | |||
+ | |- | ||
+ | | style="text-align:center" | 5 | ||
+ | | style="text-align:center" | 10 | ||
+ | | style="text-align:center" | 10 | ||
+ | | style="text-align:center" | 1.00 | ||
+ | | style="text-align:center" | Our estimates are fairly accurate. Project schedule is on track. No action required | ||
+ | |||
+ | |- | ||
+ | | style="text-align:center" | 6 | ||
+ | | style="text-align:center" | 11 | ||
+ | | style="text-align:center" | 13 | ||
+ | | style="text-align:center" | 0.85 | ||
+ | | style="text-align:center" | 2 Developers were called up for ICT (In-camp training) from 7 December onwards, lasting for a week. Despite efforts to mitigate the impact, development was delayed for 2 days. 2 buffer days were used. | ||
<!--CONTENT END--> | <!--CONTENT END--> |
Revision as of 14:17, 21 December 2015
Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
---|
Schedule Metric Score & Description
Sprint | Estimated no. of days | Actual no. of days | Metric Score | Description |
---|---|---|---|---|
1 | 8 | 8 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
2 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
3 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
4 | 15 | 15 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
5 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
6 | 11 | 13 | 0.85 | 2 Developers were called up for ICT (In-camp training) from 7 December onwards, lasting for a week. Despite efforts to mitigate the impact, development was delayed for 2 days. 2 buffer days were used. |