Difference between revisions of "IS480 Team wiki: 2015T2 Starteur Project Schedule Metrics"
Jump to navigation
Jump to search
Line 129: | Line 129: | ||
|- | |- | ||
| style="text-align:center" | 11 | | style="text-align:center" | 11 | ||
− | | style="text-align:center" | | + | | style="text-align:center" | 7 |
− | | style="text-align:center" | | + | | style="text-align:center" | 7 |
− | | style="text-align:center" | | + | | style="text-align:center" | 1 |
− | | style="text-align:center" | | + | | style="text-align:center" | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
|- | |- | ||
| style="text-align:center" | 12 | | style="text-align:center" | 12 | ||
− | | style="text-align:center" | | + | | style="text-align:center" | 16 |
− | | style="text-align:center" | | + | | style="text-align:center" | 16 |
− | | style="text-align:center" | | + | | style="text-align:center" | 1 |
− | | style="text-align:center" | | + | | style="text-align:center" | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
|- | |- | ||
| style="text-align:center" | 13 | | style="text-align:center" | 13 | ||
− | | style="text-align:center" | | + | | style="text-align:center" | 13 |
− | | style="text-align:center" | | + | | style="text-align:center" | 13 |
− | | style="text-align:center" | | + | | style="text-align:center" | 1 |
− | | style="text-align:center" | | + | | style="text-align:center" | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
|- | |- |
Latest revision as of 09:09, 30 March 2016
Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
---|
Schedule Metric Score & Description
Iteration | Estimated no. of days | Actual no. of days | Metric Score | Description |
---|---|---|---|---|
1 | 8 | 8 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
2 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
3 | 10 | 10 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required |
4 | 15 | 15 | 1.00 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
5 | 10 | 11 | 0.91 | Our estimates are fairly accurate. Project schedule is on track. 1 buffer day used to debug Email Access Codes due to complexity in number of possible scenarios with different type of users (students) |
6 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
7 | 12 | 12 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
8 | 13 | 14 | 0.93 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
9 | 12 | 9 | 1.33 | Iteration ended early as Batch Report module was pushed back due to client's inability to provide algorithm on time. Team decided to change schedule and Supervisor was informed of changes. |
10 | 9 | 9 | 1 | Our estimates are fairly accurate. Project schedule is on track. No action required. |
11 | 7 | 7 | 1 | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
12 | 16 | 16 | 1 | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
13 | 13 | 13 | 1 | Our estimates are fairly accurate. Project Schedule is on track. No action required. |
14 |