IS480 Team wiki: 2015T2 Starteur Project Change Management
Schedule | Schedule Metrics | Bug Metrics | Risk Management | Change Management |
---|
Changes Made
Description | Source | Analysis | Details |
---|---|---|---|
Dropping of functions: Sort users in group, filter users in group | External | Feasibility - High, Priority - Medium |
1. Educators in UAT 1 reflected that these 2 functions may not be useful as students would have been sorted into the different batches and as such, there is no need for them to additionally filter or sort students. |
Adding of function: Multiple Group Report | External | Feasibility - Medium, Priority - High |
1. Educators in UAT 1 reflected that they would like to be able to view multiple groups of student as a cohort so that they can compare how cohorts would differ from each other. |
Removal of Test Report visualization | Internal | Feasibility - High, Priority - High |
Team is calling Student Test Report directly from Starteur, thus, no need for visualization. |
Change Track completion rate to Track status of access code | External | Feasibility - High, Priority - High |
Educators do not need to know where their students are at in the Starteur test and prefer to know if their student has/have not completed their test, or even have an access code so that they can do something e.g. assign an access code or send a reminder. |
Change of test reminder email from automated to manual | External | Feasibility - High, Priority - Medium |
Educators want to have control over the frequency and threshold of sending out the reminder emails. |
Shifting View Payment History and Generate Invoice to Payment Gateway Module | Internal | Feasibility - Medium, Priority - Medium |
These 2 functions will only be fully completed once 3rd party payment system has been integrated. |
1. Pushing back Group Report module & User Testing for Student Test Report & Group report module till after midterms |
Internal | Feasibility - High, Priority - High |
Inputs for Group Report module are not ready and Starteur is not ready for integration. Thus, in order to not affect development schedule, modules that are not dependent on Starteur or any inputs were moved forward. As a result of the changes, User Testing 2's focus has been shifted on the Client Administrator + Discount & Promotion module. |