Project Progress
- Team is currently progressing into the secondary module - Accessibility Module
- Schedule is categorized in Phases, followed by Iterations in each Phases, to give a better overview on what the Team aims to achieve for each stage of development.
- Everyone was busy during December 2014, hence phase was altered to Technology Exploration Phase, to explore technologies required for this project.
- Phase 3 ended one week later than scheduled given new scopes were added into Data-Visualization Module in preparation for the first User Experience Test with URA, the Stakeholder.
- Two out of four testing sessions were conducted. The objectives for these testing sessions were to gather User Experience feedback on the user interface of the application.
Project Management
Project Status
Project Schedule (Plan Vs Actual)
Project Schedule (Plan Vs Actual) - Acceptance
Further changes that were made:
- Added phases to the schedule as a top-level overview for each iterations. The purpose of this is to give an overview of the development progress for the project.
- Schedule has been edited after the first iteration in the picture above. The newly edited planned schedule is shown below.
Project Schedule (Plan Vs Actual) - Mid-Term
Overall | |||||||||
---|---|---|---|---|---|---|---|---|---|
Phase | Iteration | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
[1] Requirements Gathering | 1 | 30 days | 06/10/2014 | 05/11/2014 | 37 days | 06/10/2014 | 12/11/2014 | 7 days | Review application after acceptance. Reviewed schedule for iteration 2. |
[2] Technology Exploration | 2 | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | Different personal schedules for every teammates as everyone was travelling. Tasks were switched to research module to explore the technologies used for this project. |
[3] Wire-frames and Mockup Designs | 3 | 21 days | 01/01/2015 | 21/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 10 days | Increased in scope for Data-Visualization module, and stopped development to solve high impact bugs found. |
[4] Architecture Designs | 4 | 21 days | 01/02/2015 | 21/02/2015 | 21 days | 01/02/2015 | 21/02/2015 | 0 days | On track |
Phase 1: Requirements Gathering | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 1 | 30 days | 06/10/2014 | 05/11/2014 | 37 days | 06/10/2014 | 12/11/2014 | 7 days | Review application after acceptance. Reviewed schedule for iteration 2. |
Bootstrap Module | ||||||||
CSV file upload | 3 days | 22/10/2014 | 24/10/2014 | 3 days | 22/10/2014 | 24/10/2014 | 0 days | NA |
Convert data into GeoJSON objects | 2 days | 25/10/2014 | 26/10/2014 | 2 days | 25/10/2014 | 26/10/2014 | 0 days | NA |
Geo-Visualization Module | ||||||||
Pin-Mapping, Tool-tip, Interactive Legend and Clustering | 3 days | 28/10/2014 | 30/10/2014 | 3 days | 28/10/2014 | 30/10/2014 | 0 days | NA |
Testing and Debugging | ||||||||
Regression testing | 1 day | 31/10/2014 | 31/10/2014 | 1 day | 31/10/2014 | 31/10/2014 | 0 days | NA |
Debugging | 3 day | 1/11/2014 | 3/10/2014 | 4 day | 1/10/2014 | 4/10/2014 | 1 days | NA |
Phase 2: Technology Exploration | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 2 | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | Different personal schedules for every teammates as everyone was travelling. Tasks were switched to research module to explore the technologies used for this project. |
Research Module | ||||||||
Heatmap and Chloropleth | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Database Selection and Design | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Charts and D3 Graphs | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Phase 3: Wire-frames and Mockup Designs | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 3 | 21 days | 01/01/2015 | 21/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 10 days | Increased in scope for Data-Visualization module, and stopped development to solve high impact bugs found. |
Research Module | ||||||||
PostGIS architecture | 31 days | 01/01/2015 | 31/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 0 days | NA |
Leaflet and mapping | 31 days | 01/01/2015 | 31/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 0 days | NA |
Data-Visualization Module | ||||||||
Line Chart | 4 days | 06/01/2015 | 09/01/2015 | 8 days | 06/01/2015 | 13/01/2015 | 4 days | Stopped development and solved bug. |
Histogram | 3 days | 14/01/2015 | 16/01/2015 | 3 days | 14/01/2015 | 16/01/2015 | 0 days | NA |
Box Plot | New task | 4 days | 16/01/2015 | 19/01/2015 | 0 days | NA | ||
Pie Chart | New task | 4 days | 20/01/2015 | 23/01/2015 | 0 days | NA | ||
Testing and Debugging | ||||||||
Testing: User Experience Test at URA | 1 day | 28/01/2015 | 28/01/2015 | 1 day | 28/01/2015 | 28/01/2015 | 0 days | NA |
Debugging: Dynamic interaction of charts and map | 3 day | 29/01/2015 | 31/01/2015 | 3 day | 29/01/2015 | 31/01/2015 | 0 days | NA |
Phase 4: Architecture Designs | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 4 | 21 days | 01/02/2015 | 21/02/2015 | 21 days | 01/02/2015 | 21/02/2015 | 0 days | NA |
Geo-Processing Module | ||||||||
Develop schema for database | 2 days | 01/02/2015 | 02/02/2015 | 3 days | 01/02/2015 | 03/02/2015 | 1 day | This belongs to scripting instead of diagram. |
Converting Geo JSON to X,Y Coordinates | 2 days | 03/02/2015 | 04/02/2015 | 2 days | 04/02/2015 | 05/02/2015 | 0 days | NA |
Import facility database | 2 days | 05/02/2015 | 06/02/2015 | 4 days | 06/02/2015 | 09/02/2015 | 0 days | NA |
Implement geospatial joint | 3 days | 07/02/2015 | 09/02/2015 | 3 days | 10/02/2015 | 12/02/2015 | 0 days | NA |
Import result into database | 1 day | 10/02/2015 | 10/02/2015 | Pushed to next iteration | 0 days | NA | ||
Geo-Visualization Module | ||||||||
Generate heatmap for accessibility index | 2 days | 11/02/2015 | 12/02/2015 | Pushed to next iteration | 0 days | NA | ||
Polygon selection on map with dynamic charting | New Task | 7 days | 11/02/2015 | 15/02/2015 | 3 days | NA | ||
Data-Visualization Module | ||||||||
Time Series Charts with horizontal line to reflect on percentile level | 2 days | 07/02/2015 | 08/02/2015 | 3 days | 07/02/2015 | 09/02/2015 | 0 days | NA |
Box plot with selectable outliers | 3 days | 10/02/2015 | 12/02/2015 | 4 days | 10/02/2015 | 13/02/2015 | 0 days | NA |
Dynamic charting per region interacting with map | 2 days | 17/02/2015 | 19/02/2015 | 2 days | 17/02/2015 | 19/02/2015 | 0 days | On track |
Scatter plot on price vs accessibility index | 3 days | 14/02/2015 | 16/02/2015 | Pushed to next iteration | 0 days | NA | ||
Testing and Debugging | ||||||||
Testing: User Experience Test at URA | 1 day | 12/02/2015 | 12/02/2015 | 1 day | 12/02/2015 | 12/02/2015 | 0 days | NA |
Debugging: Results of specific selection on dates reflecting on charts and map | 4 day | 13/02/2015 | 16/02/2015 | 4 day | 13/02/2015 | 16/02/2015 | 0 days | NA |