Difference between revisions of "IS480 Team wiki: 2015T2 REALIS - Mid-Term"
Jump to navigation
Jump to search
Line 48: | Line 48: | ||
====<font face = "Trebuchet MS" color="#000000"><b>Project Schedule (Plan Vs Actual) - Mid-Term</b></font>==== | ====<font face = "Trebuchet MS" color="#000000"><b>Project Schedule (Plan Vs Actual) - Mid-Term</b></font>==== | ||
− | [[Image:REALIS_ProjectSchedule_MidTerm_PvA.png|center|900px|link=]] | + | [[Image:REALIS_ProjectSchedule_MidTerm_PvA.png|center|900px|link=]]<br> |
+ | [[Image:REALIS_ProjectSchedule_MidTerm_Scope.png|center|900px|link=]]<br> | ||
+ | [[Image:REALIS_ProjectSchedule_MidTerm_GranttChart.png|center|900px|link=]] | ||
===<font face = "Trebuchet MS" color="#000000"><b>Project Metrics</b></font>=== | ===<font face = "Trebuchet MS" color="#000000"><b>Project Metrics</b></font>=== |
Revision as of 12:44, 22 February 2015
HOME | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION | THE TEAM |
MAIN | MID-TERM | FINAL |
---|
Project Progress
- Team is currently progressing into the secondary module - Accessibility Module
- Schedule is categorized in Phases, followed by Iterations in each Phases, to give a better overview on what the Team aims to achieve for each stage of development.
- Everyone was busy during December 2014, hence phase was altered to Technology Exploration Phase, to explore technologies required for this project.
- Phase 3 ended one week later than scheduled given new scopes were added into Data-Visualization Module in preparation for the first User Experience Test with URA, the Stakeholder.
- Two out of four testing sessions were conducted. The objectives for these testing sessions were to gather User Experience feedback on the user interface of the application.
Project Management
Project Status
Project Schedule (Plan Vs Actual)
Project Schedule (Plan Vs Actual) - Acceptance
Further changes that were made:
- Added phases to the schedule as a top-level overview for each iterations. The purpose of this is to give an overview of the development progress for the project.
- Schedule has been edited after the first iteration in the picture above. The newly edited planned schedule is shown below.
Project Schedule (Plan Vs Actual) - Mid-Term