Overview
We have completed the primary functionalities of the project scope - the primary architecture of the for each modules. We are currently progressing into the secondary module - Accessibility Module. The project schedule is segregated into different phases to provide an overview for each development phase.
Project Progress
Scope Changes:
- Schedule is categorized in Phases, followed by Iterations in each Phases, to give a better overview on what the Team aims to achieve for each stage of development.
Time Constraint:
- Time was required to explore new technologies for the application such as D3 library for Data-Visualization Module, Leaflet for Geo-Visualization Module and PostGIS for Geo-Processing Module.
- Increased complexity in Phase 3, for Data-Visualization, in preparation for the first User Experience Test with URA to gather feedback on application.
Technical Difficulties:
- Processing filtered data sets in PostGIS database.
Project Management
Project Status
Changes that were made:
- Made Tabular View Module part of Data-Visualization Module because this involves just developing of a simple table.
- Made Coordinate Linked View Module part of Geo-Visualization Module because this involves interaction between clicking of icons on the map with the charts.
- Replaced Analytics Module with Accessibility Module because URA already has a group of Masters students helping them in this area.
About Accessibility Module:
This module involves identifying the accessibility of a property to the nearby facilities. The identified facilities serves the primary needs of the residents, based on walkability or transport. These facilities include bus-stops, primary and secondary schools, parks, community centers, etc. The purpose of having an Accessibility Index is to observe the relationship between Accessibility with the price of the Property.
Given that the main focus of this project is building PostGIS database, this module will be heavily reliant on PostGIS database through processing calculations at the back-end. Further explanation on PostGIS architecture will be in Technical Complexity.
Project Schedule (Plan Vs Actual)
Project Schedule (Plan Vs Actual) - Acceptance
Comments by The Team:
- Scope of modules were overlooked. Some were too simple, while the rest were too complex.
- Completion of modules were not ranked based on the primary to secondary needs. Instead, modules scheduled based on the importance and simplicity.
- The team was unclear of the requirements and scope when this was planned, however, changes were made along the way, reflecting on the completion deadline of each modules.
Changes that were made:
- Added phases to the schedule as a top-level overview for each iterations. The purpose of this is to give an overview of the development progress for the project.
- Schedule has been edited after the first iteration in the picture above. The newly edited planned schedule is shown below.
Project Schedule (Plan Vs Actual) - Mid-Term
Overall | |||||||||
---|---|---|---|---|---|---|---|---|---|
Phase | Iteration | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
[1] Requirements Gathering | 1 | 30 days | 06/10/2014 | 05/11/2014 | 37 days | 06/10/2014 | 12/11/2014 | 7 days | Review application after acceptance. Reviewed schedule for iteration 2. |
[2] Technology Exploration | 2 | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | Different personal schedules for every teammates as everyone was travelling. Tasks were switched to research module to explore the technologies used for this project. |
[3] Wire-frames and Mockup Designs | 3 | 21 days | 01/01/2015 | 21/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 10 days | Increased in scope for Data-Visualization module, and stopped development to solve high impact bugs found. |
[4] Architecture Designs | 4 | 21 days | 01/02/2015 | 21/02/2015 | 21 days | 01/02/2015 | 21/02/2015 | 0 days | On track |
Phase 1: Requirements Gathering | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 1 | 30 days | 06/10/2014 | 05/11/2014 | 37 days | 06/10/2014 | 12/11/2014 | 7 days | Review application after acceptance. Reviewed schedule for iteration 2. |
Bootstrap Module | ||||||||
CSV file upload | 3 days | 22/10/2014 | 24/10/2014 | 3 days | 22/10/2014 | 24/10/2014 | 0 days | NA |
Convert data into GeoJSON objects | 2 days | 25/10/2014 | 26/10/2014 | 2 days | 25/10/2014 | 26/10/2014 | 0 days | NA |
Geo-Visualization Module | ||||||||
Pin-Mapping, Tool-tip, Interactive Legend and Clustering | 3 days | 28/10/2014 | 30/10/2014 | 3 days | 28/10/2014 | 30/10/2014 | 0 days | NA |
Testing and Debugging | ||||||||
Regression testing | 1 day | 31/10/2014 | 31/10/2014 | 1 day | 31/10/2014 | 31/10/2014 | 0 days | NA |
Debugging | 3 day | 1/11/2014 | 3/10/2014 | 4 day | 1/10/2014 | 4/10/2014 | 1 days | NA |
Phase 2: Technology Exploration | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 2 | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | Different personal schedules for every teammates as everyone was travelling. Tasks were switched to research module to explore the technologies used for this project. |
Research Module | ||||||||
Heatmap and Chloropleth | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Database Selection and Design | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Charts and D3 Graphs | 48 days | 13/11/2014 | 31/12/2014 | 48 days | 13/11/2014 | 31/12/2014 | 0 days | NA |
Phase 3: Wire-frames and Mockup Designs | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 3 | 21 days | 01/01/2015 | 21/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 10 days | Increased in scope for Data-Visualization module, and stopped development to solve high impact bugs found. |
Research Module | ||||||||
PostGIS architecture | 31 days | 01/01/2015 | 31/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 0 days | NA |
Leaflet and mapping | 31 days | 01/01/2015 | 31/01/2015 | 31 days | 01/01/2015 | 31/01/2015 | 0 days | NA |
Data-Visualization Module | ||||||||
Line Chart | 4 days | 06/01/2015 | 09/01/2015 | 8 days | 06/01/2015 | 13/01/2015 | 4 days | Stopped development and solved bug. |
Histogram | 3 days | 14/01/2015 | 16/01/2015 | 3 days | 14/01/2015 | 16/01/2015 | 0 days | NA |
Box Plot | New task | 4 days | 16/01/2015 | 19/01/2015 | 0 days | NA | ||
Pie Chart | New task | 4 days | 20/01/2015 | 23/01/2015 | 0 days | NA | ||
Testing and Debugging | ||||||||
Testing: User Experience Test at URA | 1 day | 28/01/2015 | 28/01/2015 | 1 day | 28/01/2015 | 28/01/2015 | 0 days | NA |
Debugging: Dynamic interaction of charts and map | 3 day | 29/01/2015 | 31/01/2015 | 3 day | 29/01/2015 | 31/01/2015 | 0 days | NA |
Phase 4: Architecture Designs | ||||||||
---|---|---|---|---|---|---|---|---|
Task | Planned Duration | Planned Start | Planned End | Actual Duration | Actual Start | Actual End | Delay | Comments |
Iteration 4 | 21 days | 01/02/2015 | 21/02/2015 | 21 days | 01/02/2015 | 21/02/2015 | 0 days | NA |
Geo-Processing Module | ||||||||
Develop schema for database | 2 days | 01/02/2015 | 02/02/2015 | 3 days | 01/02/2015 | 03/02/2015 | 1 day | This belongs to scripting instead of diagram. |
Converting Geo JSON to X,Y Coordinates | 2 days | 03/02/2015 | 04/02/2015 | 2 days | 04/02/2015 | 05/02/2015 | 0 days | NA |
Import facility database | 2 days | 05/02/2015 | 06/02/2015 | 4 days | 06/02/2015 | 09/02/2015 | 0 days | NA |
Implement geospatial joint | 3 days | 07/02/2015 | 09/02/2015 | 3 days | 10/02/2015 | 12/02/2015 | 0 days | NA |
Import result into database | 1 day | 10/02/2015 | 10/02/2015 | Pushed to next iteration | 0 days | NA | ||
Geo-Visualization Module | ||||||||
Generate heatmap for accessibility index | 2 days | 11/02/2015 | 12/02/2015 | Pushed to next iteration | 0 days | NA | ||
Polygon selection on map with dynamic charting | New Task | 7 days | 11/02/2015 | 15/02/2015 | 3 days | NA | ||
Data-Visualization Module | ||||||||
Time Series Charts with horizontal line to reflect on percentile level | 2 days | 07/02/2015 | 08/02/2015 | 3 days | 07/02/2015 | 09/02/2015 | 0 days | NA |
Box plot with selectable outliers | 3 days | 10/02/2015 | 12/02/2015 | 4 days | 10/02/2015 | 13/02/2015 | 0 days | NA |
Dynamic charting per region interacting with map | 2 days | 17/02/2015 | 19/02/2015 | 2 days | 17/02/2015 | 19/02/2015 | 0 days | On track |
Scatter plot on price vs accessibility index | 3 days | 14/02/2015 | 16/02/2015 | Pushed to next iteration | 0 days | NA | ||
Testing and Debugging | ||||||||
Testing: User Experience Test at URA | 1 day | 12/02/2015 | 12/02/2015 | 1 day | 12/02/2015 | 12/02/2015 | 0 days | NA |
Debugging: Results of specific selection on dates reflecting on charts and map | 4 day | 13/02/2015 | 16/02/2015 | 4 day | 13/02/2015 | 16/02/2015 | 0 days | NA |
Project Metrics
Schedule Metric
Bugs Metric
Project Risks
Technical Complexity
Quality of Product
Intermediate Deliverables
Stage | Specification | Modules |
Project Management | Minutes | Minutes |
Schedule Metrics | Metrics | |
Requirements | Design Specifications | Project Scope |
Analysis | Use case | Use case Diagram |
Architecture Diagram | Architecture Diagram | |
Workflow Diagram | Workflow Diagram | |
Design | UI Mockups | UI Mockups |
Testing | User test plan | User Tests |
Deployment
Testing
29 January 2015 & 12 February 2015 : User Experience Test | |||
---|---|---|---|
Objective | Questions Asked | Feedback | Solution |
To gather user experience feedback on the prototype after demonstrating the application to the participants. |
|
3 Property Analysts and 2 IT System Analysts
3 Physical Planners
|
|