Line 72: | Line 72: | ||
*Integration with Trello was a lot tougher than expected | *Integration with Trello was a lot tougher than expected | ||
*Actual learning curve for email function was a lot higher | *Actual learning curve for email function was a lot higher | ||
+ | * Delay in product list submission by client | ||
<br> | <br> | ||
Line 199: | Line 200: | ||
Update the proposal assumptions and risks. Describe what you learn from the risk update and mitigation steps taken. | Update the proposal assumptions and risks. Describe what you learn from the risk update and mitigation steps taken. | ||
+ | |||
+ | Can talk about how the client delayed the product list submission causing us to push the module one iteration later. | ||
{| border="1" | {| border="1" |
Revision as of 19:07, 9 February 2015
Contents
Project Progress Summary
You may download and view our midterm presentation slides here:
Midterm Presentation Slides
Project Highlights
Unexpected events that have occurred:
- Could not access SVN in China
- List of major changes to be made from December holidays and UATs:
- Revamped simulation calendar feature
- Changed cards to boards in Trello
- Added task approval from Trello
- Added email task rejection
- Added sign/pay functions for documents
- Added seal invoice function
- Deploying on DigitalOcean instead of AWS
- Implemented security features for secured data transmission
- Took longer than expected to complete document master setup
- Integration with Trello was a lot tougher than expected
- Actual learning curve for email function was a lot higher
- Delay in product list submission by client
In a Nutshell
Project Management
Project Status
Along the way, changes have been made to the scope and schedule based on client's requirements and UAT feedback. The table below displays the list of changes made since acceptance.
Category | Task/Features | Status | Confident Level (0-1) | Remark |
Schedule | News Feed | 0% | 0.75 | Shifted news feed to after midterm. |
System | Change Trello Cards to Boards | Fully implemented | 0.5 | Client's request to change card to board. Team unfamiliar with it. Yixi and Annan to research on this. |
System | Task Approval | Fully implemented | 1 | Client's request to allow project managers to approve tasks from Trello. |
System | Send Email for Rejected Tasks | Fully implemented | 1 | Adopted based on supervisor's suggestion. |
System | Sign/Pay Document | Fully implemented | 1 | Client's request to have sign/pay feature for documents. |
System | Seal Invoice | Fully implemented | 0.25 | A technical hurdle for the team due to unfamiliar technology. Li Dan and Yining to work on this. |
System | ||||