IS480 Team wiki: 2015T2 Creovate Mid Term

From IS480
Jump to navigation Jump to search

Creovate.JPG

HomeButton.png Home Aboutus.png About Us Glyphicons 042 pie chart.png Project Overview Calendaricon.png Project Management Tableicon.png Project Documentation


Acceptance Wiki Mid Term Wiki Final Wiki


Check out our Midterm Presentation Slides!

Download here: Creovate Midterm Powerpoint Slides



Check out our deployed system!

Click here: Case Management System (CAMANS)

username: superadmin
password: pa55word

Project Overview

Current Status

CurrentProgress.JPG


Development Progress


CreovateProgress1.JPG
CreovateProgress2.JPG


User Test

User Acceptance Test 1

We conducted first UAT on 11th December 2014 with 7 users from TWC2.

Please check details documentation and test result analysis here: https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2015T2_Creovate_User_Test

User Acceptance Test 2

We conducted second UAT on 22nd January 2015 with 8 users;3 administrators and 5 specialists from TWC2.

Please check details documentation and test result analysis here: https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2015T2_Creovate_User_Test

Student Heuristic Test

We conducted heuristic test with SMU students on 19th January 2015 with 10 students from different faculties from SMU.

Please check details documentation and test result analysis here: https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2015T2_Creovate_User_Test

Technical Complexity

System Diagram

CreovateSystemArchitechture.png


Complexity

CreovateTechnicalComplexity.png

Data Analytic Prototype

Data Analytic.PNG


Project Management

Plan Vs Actual


CreovateScope.png
CreovateActualScope.JPG


Project Schedule:


CreovateSchedule4.JPG


Metric Management

Check our metric scores here: https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2015T2_Creovate_Metric

Future Risks


CreovateFutureRisks.JPG


Reflection


Kyi Lai Lai Shoon - "I used to think keeping all the metric records and scores is very tedious and brings extra work. However, as I have been working on this project, I find that the metric helps me a lot in giving overview of exactly where we are and what we need to do next in order to meet our target. By planning out the schedule way ahead, I can easily make decision in the event of changes and crisis. Moreover, it is not always easy to make all the stakeholders happy so I try my best to work together with the client as well as my own team members."

Soe Myat Myat - " Through this project, I learnt how to negotiate with the client and strike the balance between client's expectation and what I can do. I learnt various technologies such as Ajax, JQuery and how to applied them in the project. In addition, I learnt how it is like to handle the deployment of app in linux server. Most of all, I learnt how to code elegantly and handle the changes in most effective way."