IS480 Team wiki: 2015T1 Vulcan Project Management
Revision as of 22:46, 16 August 2015 by Weiting.low.2013 (talk | contribs)
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Simplified Project Schedule
Iteration | Date | Milestones | Status |
---|---|---|---|
0 | 18 May 2015 - 17 Jun 2015 | Proposal (17 Jun 2015) | Completed |
1 | 18 Jun 2015 - 5 Jul 2015 | Completed | |
2 | 7 Jul 2015 - 7 Aug 2015 | Completed | |
3 | 8 Aug 2015 - 17 Aug 2015 | User Testing 1 (13 Aug 2015) Acceptance (17 Aug 2015) |
In Progress |
4 | 18 Aug 2015 - 4 Sep 2015 | Registration (20 Aug 2015) | Not Started |
5 | 5 Sep 2015 - 18 Sep 2015 | Not Started | |
6 | 19 Sep 2015 - 4 Oct 2015 | User Testing 2 (22 Sep 2015) | Not Started |
7 | 5 Oct 2015 - 25 Oct 2015 | Mid Term (5 Oct 2015 - 9 Oct 2015) | Not Started |
8 | 26 Oct 2015 - 31 Oct 2015 | User Testing 3 (29 Oct 2015) | Not Started |
9 | 1 Nov 2015 - 9 Nov 2015 | Poster (9 Nov 2015) | Not Started |
10 | 10 Nov 2015 - 16 Nov 2015 | User Testing 4 (16 Nov 2015) | Not Started |
11 | 17 Nov 2015 - 3 Dec 2015 | Finals (23 Nov 2015) Poster Day (3 Dec 2015) |
Not Started |
Project Schedule