We are currently at Iteration 5.
Line 65: | Line 65: | ||
|Completed | |Completed | ||
|- | |- | ||
− | |<b> | + | |5 |
− | |<b> | + | |11 Sep 2015 - 24 Sep 2015 |
− | |<b> | + | |User Testing 2 (18 Aug 2015) |
− | + | User Testing 3 (22 Aug 2015) | |
+ | |Completed | ||
+ | |- | ||
+ | |<b>6</b> | ||
+ | |<b>25 Sep 2015 - 8 Oct 2015</b> | ||
+ | |<b>Mid Term (7 Oct 2015) <br> | ||
+ | Alpha Launch on Playstore / Testing (2 Oct 2015) | ||
|<b>In Progress</b> | |<b>In Progress</b> | ||
− | |||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
|7 | |7 | ||
Line 82: | Line 83: | ||
|- | |- | ||
|8 | |8 | ||
− | |23 Oct 2015 - | + | |23 Oct 2015 - 5 Nov 2015 |
− | |User Testing 4 ( | + | |User Testing 4 (23 Oct 2015)<br> |
+ | Move to Production Server (30 Oct 2015)<br> | ||
+ | Beta Launch on Playstore / Testing (5 Nov 2015) | ||
|Not Started | |Not Started | ||
|- | |- | ||
|9 | |9 | ||
− | | | + | |6 Nov 2015 - 19 Nov 2015 |
− | |Poster (9 Nov 2015) | + | |Poster (9 Nov 2015)<br> |
+ | User Testing 5 (10 Nov 2015)<br> | ||
+ | Publish App on Playstore (16 Nov 2015) | ||
|Not Started | |Not Started | ||
|- | |- | ||
|10 | |10 | ||
− | | | + | |20 Nov 2015 - 3 Dec 2015 |
− | + | |Finals (23 Nov 2015) <br> Poster Day (3 Dec 2015) | |
− | |||
− | |||
− | |||
− | |||
− | |Finals (23 Nov 2015) <br> | ||
|Not Started | |Not Started | ||
|- | |- |
Revision as of 13:55, 6 October 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Simplified Project Schedule
Iteration | Date | Milestones | Status |
---|---|---|---|
0 | 18 May 2015 - 17 Jun 2015 | Proposal (17 Jun 2015) | Completed |
1 | 18 Jun 2015 - 5 Jul 2015 | Completed | |
2 | 7 Jul 2015 - 7 Aug 2015 | Completed | |
3 | 8 Aug 2015 - 17 Aug 2015 | User Testing 1 (13 Aug 2015) Acceptance (17 Aug 2015) |
Completed |
4 | 18 Aug 2015 - 10 Sep 2015 | Registration (20 Aug 2015) | Completed |
5 | 11 Sep 2015 - 24 Sep 2015 | User Testing 2 (18 Aug 2015)
User Testing 3 (22 Aug 2015) |
Completed |
6 | 25 Sep 2015 - 8 Oct 2015 | Mid Term (7 Oct 2015) Alpha Launch on Playstore / Testing (2 Oct 2015) |
In Progress |
7 | 9 Oct 2015 - 22 Oct 2015 | Not Started | |
8 | 23 Oct 2015 - 5 Nov 2015 | User Testing 4 (23 Oct 2015) Move to Production Server (30 Oct 2015) |
Not Started |
9 | 6 Nov 2015 - 19 Nov 2015 | Poster (9 Nov 2015) User Testing 5 (10 Nov 2015) |
Not Started |
10 | 20 Nov 2015 - 3 Dec 2015 | Finals (23 Nov 2015) Poster Day (3 Dec 2015) |
Not Started |
Project Schedule