Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned (Android App and Smart Watch). Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
4 | 18 | 24 | 75% | Team is behind schedule. This is due to Livelab's server permission issues. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
5 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
6 | 14 | ?? | 100% | ?? | In Progress |
Schedule Metrics Results
Bug Metrics
For detailed bug reports, please click the links below to download the detailed bug metrics:
Bug Metric Iteration 1
Bug Metric Iteration 2
Bug Metric Iteration 3
Bug Metric Iteration 4
Bug Metric Iteration 5
Bug Metric Iteration 6
Bug Metric Iteration 7
Bug Metric Iteration 8
Change Management Metrics