Line 99: | Line 99: | ||
<div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Bug Metrics</font></div> | <div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Bug Metrics</font></div> | ||
<br> | <br> | ||
− | [[File: vulcan_bugmetric.PNG|center| | + | [[File: vulcan_bugmetric.PNG|center|700px|link=]] |
<br> | <br> | ||
[[File:Vulcan_Bug_Report_3.png|center|550px|link=]] | [[File:Vulcan_Bug_Report_3.png|center|550px|link=]] |
Revision as of 00:28, 7 October 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned (Android App and Smart Watch). Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
4 | 18 | 24 | 75% | Team is behind schedule. This is due to Livelab's server permission issues. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
5 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
6 | 14 | ?? | 100% | ?? | In Progress |
Schedule Metrics Results
Bug Metrics
For detailed bug reports, please click the links below to download the detailed bug metrics:
Bug Metric Iteration 1
Bug Metric Iteration 2
Bug Metric Iteration 3
Bug Metric Iteration 4
Bug Metric Iteration 5
Change Management Metrics