Difference between revisions of "IS480 Team wiki: 2015T1 Vulcan Metrics"
Jump to navigation
Jump to search
(One intermediate revision by one other user not shown) | |||
Line 148: | Line 148: | ||
<br> | <br> | ||
[[Media:Vulcan_Bug_Metric_Iteration_8.xlsx| Bug Metric Iteration 8]] | [[Media:Vulcan_Bug_Metric_Iteration_8.xlsx| Bug Metric Iteration 8]] | ||
− | + | <br> | |
+ | [[Media:Vulcan_Bug_Metric_Iteration_9.xlsx| Bug Metric Iteration 9]] | ||
<br> | <br> | ||
{| <div style="padding: 5px; line-height: wrap_content; font-size:18px; font-weight: bold; border-bottom:1px solid #000000; font-family: helvetica"> | {| <div style="padding: 5px; line-height: wrap_content; font-size:18px; font-weight: bold; border-bottom:1px solid #000000; font-family: helvetica"> | ||
<div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Change Management Metrics</font></div> | <div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Change Management Metrics</font></div> | ||
[[File: Change Mgmt.png|center|720px|link=]] | [[File: Change Mgmt.png|center|720px|link=]] | ||
− | [[File: Change Requests.png|center| | + | [[File: Change Requests.png|center|1000px|link=]] |
− | [[File: Vulcan_Change_Mgmt_2.png|center| | + | [[File: Vulcan_Change_Mgmt_2.png|center|1000px|link=]] |
Latest revision as of 15:22, 22 November 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned (Android App and Smart Watch). Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
4 | 18 | 24 | 75% | Team is behind schedule. This is due to Livelab's server permission issues. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
5 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
6 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
7 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
8 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
9 | 14 | 14 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
10 | 14 | ?? | ?? | ?? | In Progress |
Schedule Metrics Results
Bug Metrics
For detailed bug reports, please click the links below to download the detailed bug metrics:
Bug Metric Iteration 1
Bug Metric Iteration 2
Bug Metric Iteration 3
Bug Metric Iteration 4
Bug Metric Iteration 5
Bug Metric Iteration 6
Bug Metric Iteration 7
Bug Metric Iteration 8
Bug Metric Iteration 9
Change Management Metrics