Difference between revisions of "IS480 Team wiki: 2015T1 Vulcan Metrics"
Jump to navigation
Jump to search
Jvchan.2013 (talk | contribs) |
Jvchan.2013 (talk | contribs) |
||
Line 84: | Line 84: | ||
<br> | <br> | ||
For detailed test cases, please click the links below to download the detailed bug metrics: | For detailed test cases, please click the links below to download the detailed bug metrics: | ||
+ | <br> | ||
[[Media:Bug Metric Iteration 1.xlsx| Bug Metric Iteration 1]] | [[Media:Bug Metric Iteration 1.xlsx| Bug Metric Iteration 1]] | ||
+ | <br> | ||
[[Media:Bug Metric Iteration 2.xlsx| Bug Metric Iteration 2]] | [[Media:Bug Metric Iteration 2.xlsx| Bug Metric Iteration 2]] | ||
+ | <br> | ||
[[Media:Bug Metric Iteration 3.xlsx| Bug Metric Iteration 3]] | [[Media:Bug Metric Iteration 3.xlsx| Bug Metric Iteration 3]] | ||
Revision as of 06:07, 17 August 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
Schedule Metrics Results
Bug Metrics
For detailed test cases, please click the links below to download the detailed bug metrics:
Bug Metric Iteration 1
Bug Metric Iteration 2
Bug Metric Iteration 3
Change Management Metrics