Difference between revisions of "IS480 Team wiki: 2015T1 Vulcan Metrics"

From IS480
Jump to navigation Jump to search
Line 82: Line 82:
 
<br>
 
<br>
 
[[File:Bug Summary.png|center|550px|link=]]
 
[[File:Bug Summary.png|center|550px|link=]]
 
+
[[Media:Bug Metric Iteration 1.xlsx|center|550px|link=]]
  
  

Revision as of 06:03, 17 August 2015

VulcanLogo.png
Vulcan home icon2.png
Vulcan aboutus icon2.png
Vulcan projectoverview icon2.png
Vulcan projectmanagement icon2.png
Vulcan documentation icon2.png

HOME ABOUT US PROJECT OVERVIEW PROJECT MANAGEMENT DOCUMENTATION


Schedule Metrics


Vulcan schedule metrics.PNG
Summary of Schedule Metrics


Iteration Planned Duration (Days) Actual Duration (Days) Schedule Metric Score Action Status
1 18 18 100% Estimates are generally accurate and on track. No action to be taken. Completed
2 18 32 56.25% Team is behind schedule. This is due to the complexity of the tasks planned.

Follow up action: Rescheduled the future iterations, deducted days from buffer days.

Completed
3 10 10 100% Estimates are generally accurate and on track. No action to be taken. Completed


Schedule Metrics Results
Vulcan Schedule Metric Score.PNG
Bug Metrics


Vulcan bugmetric.PNG


Bug Graph.png


Bug Summary.png

center|550px|link=



Change Management Metrics
Change Mgmt.png
Change Requests.png