Difference between revisions of "IS480 Team wiki: 2015T1 Vulcan Metrics"
Jump to navigation
Jump to search
Line 81: | Line 81: | ||
{| <div style="padding: 5px; line-height: wrap_content; font-size:18px; font-weight: bold; border-bottom:1px solid #000000; font-family: helvetica"> | {| <div style="padding: 5px; line-height: wrap_content; font-size:18px; font-weight: bold; border-bottom:1px solid #000000; font-family: helvetica"> | ||
<div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Change Management Metrics</font></div> | <div style="background: #6CACFF; padding: 15px; font-weight: bold; line-height: 0.3em; text-indent: 0px; font-size:20px; font-family: helvetica"><font color= #FFFFFF>Change Management Metrics</font></div> | ||
− | [[File: Change Mgmt.png|center| | + | [[File: Change Mgmt.png|center|720px|link=]] |
− | [[File: Change Requests.png|center| | + | [[File: Change Requests.png|center|768px|link=]] |
Revision as of 22:05, 16 August 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Schedule Metrics
Summary of Schedule Metrics
Iteration | Planned Duration (Days) | Actual Duration (Days) | Schedule Metric Score | Action | Status |
---|---|---|---|---|---|
1 | 18 | 18 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |
2 | 18 | 32 | 56.25% | Team is behind schedule. This is due to the complexity of the tasks planned. Follow up action: Rescheduled the future iterations, deducted days from buffer days. |
Completed |
3 | 10 | 10 | 100% | Estimates are generally accurate and on track. No action to be taken. | Completed |