Difference between revisions of "IS480 Team wiki: 2015T1 Team Big Hero 5 Task List"
Jump to navigation
Jump to search
Xyxia.2013 (talk | contribs) |
Xyxia.2013 (talk | contribs) |
||
(13 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | |||
<!--START HEADER --> | <!--START HEADER --> | ||
[[Image: Big_Hero_5_Logo.jpg|center|1000x200px]] <br> | [[Image: Big_Hero_5_Logo.jpg|center|1000x200px]] <br> | ||
Line 42: | Line 41: | ||
<!---------------------------Content Starts Here -------------------> | <!---------------------------Content Starts Here -------------------> | ||
+ | |||
+ | == Iteration 0 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''3 May 2015 to 31 May 2015 '''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | Gather requirement | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 03/05/2015 | ||
+ | | 31/05/2015 | ||
+ | |- | ||
+ | | Finalize use cases | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 03/05/2015 | ||
+ | | 31/05/2015 | ||
+ | |} | ||
+ | <br> | ||
== Iteration 1 == | == Iteration 1 == | ||
<br> | <br> | ||
− | <div><font size="4" color=B22222> ''' | + | <div><font size="4" color=B22222> '''1 June – 17 June'''</font></div> |
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | Proposal preparation | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 01/06/2015 | ||
+ | | 14/06/2015 | ||
+ | |- | ||
+ | | Schedule planning | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 01/06/2015 | ||
+ | | 14/06/2015 | ||
+ | |- | ||
+ | | Wiki | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 05/06/2015 | ||
+ | | 17/06/2015 | ||
+ | |- | ||
+ | | Research technical knowledge | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 01/06/2015 | ||
+ | | 17/06/2015 | ||
+ | |- | ||
+ | | UI mock-up | ||
+ | | Non-coding | ||
+ | | Wang Yiyi | ||
+ | | 10/06/2015 | ||
+ | | 17/06/2015 | ||
+ | |- | ||
+ | | Set up SVN | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 16/06/2015 | ||
+ | | 17/06/2015 | ||
+ | |- | ||
+ | | Metrics | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 16/06/2015 | ||
+ | | 17/06/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 2 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''18 June – 24 June'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | Login/Logout | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 18/06/2015 | ||
+ | | 19/06/2015 | ||
+ | |- | ||
+ | | Registration | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 19/06/2015 | ||
+ | | 20/06/2015 | ||
+ | |- | ||
+ | | Test Cases | ||
+ | | Non-coding | ||
+ | | Zhang Jiahang | ||
+ | | 21/06/2015 | ||
+ | | 22/06/2015 | ||
+ | |- | ||
+ | | integration& debug | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 21/06/2015 | ||
+ | | 24/06/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 3 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''25 June – 7 July'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | Push deals | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 25/06/2015 | ||
+ | | 27/06/2015 | ||
+ | |- | ||
+ | | Withdraw deals | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 27/06/2015 | ||
+ | | 01/07/2015 | ||
+ | |- | ||
+ | | Update restaurant profile | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 01/07/2015 | ||
+ | | 03/07/2015 | ||
+ | |- | ||
+ | | Update preference | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 25/06/2015 | ||
+ | | 27/06/2015 | ||
+ | |- | ||
+ | | View deals | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 27/06/2015 | ||
+ | | 03/07/2015 | ||
+ | |- | ||
+ | | Preview deals | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 25/06/2015 | ||
+ | | 27/06/2015 | ||
+ | |- | ||
+ | | Generate confirmation ID | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 27/06/2015 | ||
+ | | 03/07/2015 | ||
+ | |- | ||
+ | | Test Cases | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 05/07/2015 | ||
+ | | 05/07/2015 | ||
+ | |- | ||
+ | | Integration& Debugging | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 05/07/2015 | ||
+ | | 05/07/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | Zhang Jiahang | ||
+ | | 05/07/2015 | ||
+ | | 06/07/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 4 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''8 July – 21 July'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | finish updating Wiki Page | ||
+ | | Non-coding | ||
+ | | Xia xueying | ||
+ | | 08/07/2015 | ||
+ | | 14/07/2015 | ||
+ | |- | ||
+ | | Mock up for front page | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 08/07/2015 | ||
+ | | 08/07/2015 | ||
+ | |- | ||
+ | | Start coding UI for existing functions | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 09/07/2015 | ||
+ | | 18/07/2015 | ||
+ | |- | ||
+ | | Verify ID(Merchant) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 13/07/2015 | ||
+ | | 16/07/2015 | ||
+ | |- | ||
+ | | View favourite restaurant(Merchant) | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 10/07/2015 | ||
+ | | 13/07/2015 | ||
+ | |- | ||
+ | | Make reservation(Customer) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 08/07/2015 | ||
+ | | 13/07/2015 | ||
+ | |- | ||
+ | | Like restaurant(Customer) | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 08/07/2015 | ||
+ | | 10/07/2015 | ||
+ | |- | ||
+ | | Retrieve and convert Location and calculate distance | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 08/07/2015 | ||
+ | | 17/07/2015 | ||
+ | |- | ||
+ | | View favorite restaurant(Customer) | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 13/07/2015 | ||
+ | | 16/07/2015 | ||
+ | |- | ||
+ | | Update Last visited info | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 09/07/2015 | ||
+ | | 12/07/2015 | ||
+ | |- | ||
+ | | Test & Debug | ||
+ | | Coding | ||
+ | | Xia Xueying, Wang Yiyi | ||
+ | | 19/07/2015 | ||
+ | | 21/07/2015 | ||
+ | |- | ||
+ | | Deploy to server | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 21/07/2015 | ||
+ | | 21/07/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 5 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''22 July – 4 Aug'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take record on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 22/07/2015 | ||
+ | | 04/08/2015 | ||
+ | |- | ||
+ | | prepare for supervisor meeting | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 22/07/2015 | ||
+ | | 24/07/2015 | ||
+ | |- | ||
+ | | UI for login, merchant home, push deals, company profile | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 22/07/2015 | ||
+ | | 25/07/2015 | ||
+ | |- | ||
+ | | UI for reservation, customer main page | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 26/07/2015 | ||
+ | | 01/08/2015 | ||
+ | |- | ||
+ | | recommendation (favorite list) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 22/07/2015 | ||
+ | | 25/07/2015 | ||
+ | |- | ||
+ | | recommendation (budget) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 25/07/2015 | ||
+ | | 28/07/2015 | ||
+ | |- | ||
+ | | recommendation (cuisine type) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 28/07/2015 | ||
+ | | 01/08/2015 | ||
+ | |- | ||
+ | | push notification | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 22/07/2015 | ||
+ | | 25/07/2015 | ||
+ | |- | ||
+ | | push similar deal | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 01/08/2015 | ||
+ | | 01/08/2015 | ||
+ | |- | ||
+ | | Customer to deal travel distance | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 22/07/2015 | ||
+ | | 25/07/2015 | ||
+ | |- | ||
+ | | Code Optimization | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 01/08/2015 | ||
+ | | 02/08/2015 | ||
+ | |- | ||
+ | | test case | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 01/08/2015 | ||
+ | | 02/08/2015 | ||
+ | |- | ||
+ | | Test & Debug | ||
+ | | Non-coding | ||
+ | | Xia Xueying, Wang Yiyi | ||
+ | | 03/08/2015 | ||
+ | | 03/08/2015 | ||
+ | |- | ||
+ | | Deploy to server | ||
+ | | Non-coding | ||
+ | | All team member | ||
+ | | 04/08/2015 | ||
+ | | 04/08/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 6 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''5 August – 17 August '''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | prepare slides | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 05/08/2015 | ||
+ | | 12/08/2015 | ||
+ | |- | ||
+ | | Prepare UAT | ||
+ | | Non-coding | ||
+ | | All Team Member | ||
+ | | 06/08/2015 | ||
+ | | 11/08/2015 | ||
+ | |- | ||
+ | | UAT1 | ||
+ | | Non-coding | ||
+ | | All Team Member | ||
+ | | 12/08/2015 | ||
+ | | 13/08/2015 | ||
+ | |- | ||
+ | | UI adjustment | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 14/08/2015 | ||
+ | | 15/08/2015 | ||
+ | |- | ||
+ | | Testing & Debugging | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 14/08/2015 | ||
+ | | 15/08/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | Cao Xinge | ||
+ | | 16/08/2015 | ||
+ | | 17/08/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | == Iteration 7 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''18 August – 30 August '''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take recored on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 27/08/2015 | ||
+ | | 27/08/2015 | ||
+ | |- | ||
+ | | prepare for supervisor meeting | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 27/08/2015 | ||
+ | | 27/08/2015 | ||
+ | |- | ||
+ | | UAT1 | ||
+ | | Update UI for UAT1 | ||
+ | | Wang Yiyi | ||
+ | | 18/08/2015 | ||
+ | | 30/08/2015 | ||
+ | |- | ||
+ | | Update DB | ||
+ | | Coding | ||
+ | | Gao Yiming, Zhang Jiahang | ||
+ | | 18/08/2015 | ||
+ | | 20/08/2015 | ||
+ | |- | ||
+ | | View deals status | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 18/08/2015 | ||
+ | | 20/08/2015 | ||
+ | |- | ||
+ | | Deal template | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 25/08/2015 | ||
+ | | 28/08/2015 | ||
+ | |- | ||
+ | | send user email to confirm the registration | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 20/08/2015 | ||
+ | | 21/08/2015 | ||
+ | |- | ||
+ | | redemption history for merchant | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 22/08/2015 | ||
+ | | 24/08/2015 | ||
+ | |- | ||
+ | | Test Case | ||
+ | | Non-Coding | ||
+ | | Xia Xueying | ||
+ | | 25/08/2015 | ||
+ | | 27/08/2015 | ||
+ | |- | ||
+ | | Testing & Debugging | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 14/08/2015 | ||
+ | | 15/08/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | Cao Xinge | ||
+ | | 16/08/2015 | ||
+ | | 17/08/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | == Iteration 8 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''31 August – 14 September '''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take recored on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 31/08/2015 | ||
+ | | 02/09/2015 | ||
+ | |- | ||
+ | | Prepare UAT2 | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 31/08/2015 | ||
+ | | 02/09/2015 | ||
+ | |- | ||
+ | | update UI for UAT | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 31/08/2015 | ||
+ | | 11/08/2015 | ||
+ | |- | ||
+ | | Withdraw deals(handle user withdraw after ding) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 31/08/2015 | ||
+ | | 02/09/2015 | ||
+ | |- | ||
+ | | Deal expiration + number restriction | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 31/08/2015 | ||
+ | | 02/09/2015 | ||
+ | |- | ||
+ | | UAT improve | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 31/08/2015 | ||
+ | | 11/09/2015 | ||
+ | |- | ||
+ | | Test Case | ||
+ | | Non-Coding | ||
+ | | Xia Xueying | ||
+ | | 12/09/2015 | ||
+ | | 12/09/2015 | ||
+ | |- | ||
+ | | Testing & Debugging | ||
+ | | Coding | ||
+ | | All Team Member | ||
+ | | 13/09/2015 | ||
+ | | 13/09/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | All Team Member | ||
+ | | 14/09/2015 | ||
+ | | 14/09/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 9 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''15 September - 28 September'''</font></div> | ||
{| class="wikitable" | {| class="wikitable" | ||
! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
Line 53: | Line 608: | ||
! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
|- | |- | ||
− | | | + | | take recored on schedule |
− | | | + | | Non-coding |
− | | | + | | Xia Xueying |
− | | | + | | 15/09/2015 |
− | | | + | | 16/09/2015 |
+ | |- | ||
+ | | UAT2 | ||
+ | | Non-coding | ||
+ | | All Team Member | ||
+ | | 17/09/2015 | ||
+ | | 20/09/2015 | ||
+ | |- | ||
+ | | gather UAT feedback | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 20/09/2015 | ||
+ | | 20/09/2015 | ||
+ | |- | ||
+ | | change UI | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 20/09/2015 | ||
+ | | 27/09/2015 | ||
+ | |- | ||
+ | | reset password | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 20/09/2015 | ||
+ | | 21/09/2015 | ||
+ | |- | ||
+ | | confirmation email content | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 21/09/2015 | ||
+ | | 22/09/2015 | ||
+ | |- | ||
+ | | separate code | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 20/09/2015 | ||
+ | | 20/09/2015 | ||
+ | |- | ||
+ | | deal start time | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 21/09/2015 | ||
+ | | 22/09/2015 | ||
+ | |- | ||
+ | | shorten the redemption step | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 21/09/2015 | ||
+ | | 22/09/2015 | ||
+ | |- | ||
+ | | manage deal template | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 22/09/2015 | ||
+ | | 24/09/2015 | ||
+ | |- | ||
+ | | deal performance detail | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 21/09/2015 | ||
+ | | 22/09/2015 | ||
+ | |- | ||
+ | | input validation javascript | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 22/09/2015 | ||
+ | | 24/09/2015 | ||
+ | |- | ||
+ | | budget slider/distance slider | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 22/09/2015 | ||
+ | | 23/09/2015 | ||
+ | |- | ||
+ | | like company ajex | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 17/09/2015 | ||
+ | | 20/09/2015 | ||
+ | |- | ||
+ | | Test Case | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 26/09/2015 | ||
+ | | 26/09/2015 | ||
+ | |- | ||
+ | | Testing & Debugging | ||
+ | | Coding | ||
+ | | All Team Members | ||
+ | | 27/09/2015 | ||
+ | | 27/09/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | All Team Members | ||
+ | | 28/09/2015 | ||
+ | | 28/09/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 10 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''29 September - 12 October '''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take recored on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 29/09/2015 | ||
+ | | 29/09/2015 | ||
+ | |- | ||
+ | | Prepare UAT3 | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 29/09/2015 | ||
+ | | 30/09/2015 | ||
+ | |- | ||
+ | | improve UI | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 29/09/2015 | ||
+ | | 02/10/2015 | ||
+ | |- | ||
+ | | display restaurant list | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 29/09/2015 | ||
+ | | 01/10/2015 | ||
+ | |- | ||
+ | | improve input field | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 29/09/2015 | ||
+ | | 02/10/2015 | ||
+ | |- | ||
+ | | improve function | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 29/09/2015 | ||
+ | | 02/10/2015 | ||
+ | |- | ||
+ | | UAT3 | ||
+ | | Non-coding | ||
+ | | All Team Member | ||
+ | | 03/10/2015 | ||
+ | | 03/10/2015 | ||
+ | |- | ||
+ | | gather UAT3 feedback | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 03/10/2015 | ||
+ | | 03/10/2015 | ||
+ | |- | ||
+ | | UI Changes | ||
+ | | Coding | ||
+ | | Wang Yiyi | ||
+ | | 03/10/2015 | ||
+ | | 06/10/2015 | ||
+ | |- | ||
+ | | function changes | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 03/10/2015 | ||
+ | | 05/10/2015 | ||
+ | |- | ||
+ | | midterm preparation | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 03/10/2015 | ||
+ | | 07/10/2015 | ||
+ | |- | ||
+ | | midterm presentation | ||
+ | | Non-coding | ||
+ | | All Team Members | ||
+ | | 09/10/2015 | ||
+ | | 09/10/2015 | ||
+ | |- | ||
+ | | midterm feedback gathering | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 09/10/2015 | ||
+ | | 09/10/2015 | ||
+ | |- | ||
+ | | function changes | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 10/10/2015 | ||
+ | | 10/10/2015 | ||
+ | |- | ||
+ | | Test Case | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 10/10/2015 | ||
+ | | 10/10/2015 | ||
+ | |- | ||
+ | | Testing & Debugging | ||
+ | | Coding | ||
+ | | All Team Members | ||
+ | | 11/10/2015 | ||
+ | | 12/10/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-coding | ||
+ | | All Team Members | ||
+ | | 12/10/2015 | ||
+ | | 12/10/2015 | ||
+ | |} | ||
+ | |||
+ | == Iteration 11 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''Oct 13 - Oct 26'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take recored on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 13/10/2015 | ||
+ | | 13/10/2015 | ||
+ | |- | ||
+ | | Share deal with friends (Whatsapp, Facebook) | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 13/10/2015 | ||
+ | | 15/10/2015 | ||
+ | |- | ||
+ | | Make change on deal detail page | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 13/10/2015 | ||
+ | | 16/10/2015 | ||
+ | |- | ||
+ | | Make change on deal confirmation page | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 13/10/2015 | ||
+ | | 16/10/2015 | ||
+ | |- | ||
+ | | Test Cases | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 20/10/2015 | ||
+ | | 20/10/2015 | ||
+ | |- | ||
+ | | integration & debug | ||
+ | | Coding | ||
+ | | All team members | ||
+ | | 21/10/2015 | ||
+ | | 25/10/2015 | ||
+ | |- | ||
+ | | Deploy to server | ||
+ | | Non-Coding | ||
+ | | Cao Xinge | ||
+ | | 25/10/2015 | ||
+ | | 26/10/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 12 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''Oct 27 - Nov 9'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take record on schedule | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 27/10/2015 | ||
+ | | 27/10/2015 | ||
+ | |- | ||
+ | | Generate Report (analyse reach, view, ding for a deal) | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 27/10/2015 | ||
+ | | 31/10/2015 | ||
+ | |- | ||
+ | | generate PDF | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 27/10/2015 | ||
+ | | 28/10/2015 | ||
+ | |- | ||
+ | | Scan QR code to redeem | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 28/10/2015 | ||
+ | | 29/10/2015 | ||
+ | |- | ||
+ | | Make change on push deal function | ||
+ | | Coding | ||
+ | | Zhang Jiahang | ||
+ | | 31/10/2015 | ||
+ | | 01/11/2015 | ||
+ | |- | ||
+ | | Review | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 01/11/2015 | ||
+ | | 03/11/2015 | ||
+ | |- | ||
+ | | DB change | ||
+ | | Coding | ||
+ | | Cao Xinge, Gao Yiming | ||
+ | | 28/10/2015 | ||
+ | | 30/10/2015 | ||
+ | |- | ||
+ | | Video & Poster | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 28/10/2015 | ||
+ | | 31/10/2015 | ||
+ | |- | ||
+ | | Finalize UI | ||
+ | | Non-coding | ||
+ | | Wang Yiyi | ||
+ | | 01/11/2015 | ||
+ | | 03/11/2015 | ||
+ | |- | ||
+ | | Test Cases | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 04/11/2015 | ||
+ | | 04/11/2015 | ||
+ | |- | ||
+ | | integration& debug | ||
+ | | Coding | ||
+ | | Cao Xinge | ||
+ | | 05/11/2015 | ||
+ | | 07/11/2015 | ||
+ | |- | ||
+ | | Deploy | ||
+ | | Non-Coding | ||
+ | | Cao Xinge | ||
+ | | 08/11/2015 | ||
+ | | 08/11/2015 | ||
+ | |} | ||
+ | <br> | ||
+ | |||
+ | == Iteration 13 == | ||
+ | <br> | ||
+ | <div><font size="4" color=B22222> '''Nov 10 - Nov 24'''</font></div> | ||
+ | {| class="wikitable" | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:150px" | Function | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:200px" | Category | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:300px" | Assign to | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Scheduled | ||
+ | ! style="font-weight: bold;background: #B22222;color:#ffffff; width:100px" | Date Completed | ||
+ | |- | ||
+ | | take recored on schedule | ||
+ | | Non-Coding | ||
+ | | Xia Xueying | ||
+ | | 10/11/2015 | ||
+ | | 10/11/2015 | ||
+ | |- | ||
+ | | Prepare for UAT4 | ||
+ | | Non-Coding | ||
+ | | Xia Xueying | ||
+ | | 11/11/2015 | ||
+ | | 11/11/2015 | ||
+ | |- | ||
+ | | UAT for students | ||
+ | | Non-Coding | ||
+ | | All | ||
+ | | 16/11/2015 | ||
+ | | 16/11/2015 | ||
+ | |- | ||
+ | | Gather feedback | ||
+ | | Non-Coding | ||
+ | | Xia Xueying | ||
+ | | 16/11/2015 | ||
+ | | 16/11/2015 | ||
+ | |- | ||
+ | | Debug | ||
+ | | Coding | ||
+ | | Gao Yiming | ||
+ | | 19/06/2015 | ||
+ | | 20/06/2015 | ||
+ | |- | ||
+ | | UAT for Merchants | ||
+ | | Non-Coding | ||
+ | | All | ||
+ | | 19/11/2015 | ||
+ | | 19/11/2015 | ||
+ | |- | ||
+ | | Test Cases | ||
+ | | Non-coding | ||
+ | | Xia Xueying | ||
+ | | 20/11/2015 | ||
+ | | 20/11/2015 | ||
|- | |- | ||
− | | | + | | prepare for final presentation |
− | | | + | | Non-coding |
− | | | + | | Xia Xueying |
− | | | + | | 20/11/2015 |
− | | | + | | 20/11/2015 |
|- | |- | ||
− | | | + | | integration& debug |
− | | | + | | Coding |
− | | | + | | Cao Xinge |
− | | | + | | 21/11/2015 |
+ | | 22/11/2015 | ||
|- | |- | ||
− | | | + | | Deploy |
− | | | + | | Non-coding |
− | | | + | | Gao Yiming |
− | | | + | | 22/11/2015 |
− | | | + | | 22/11/2015 |
|} | |} | ||
<br> | <br> |
Latest revision as of 22:45, 19 November 2015
Schedule | Metrics | Task List |
---|
Contents
Iteration 0
3 May 2015 to 31 May 2015
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
Gather requirement | Non-coding | All team member | 03/05/2015 | 31/05/2015 |
Finalize use cases | Non-coding | All team member | 03/05/2015 | 31/05/2015 |
Iteration 1
1 June – 17 June
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
Proposal preparation | Non-coding | All team member | 01/06/2015 | 14/06/2015 |
Schedule planning | Non-coding | All team member | 01/06/2015 | 14/06/2015 |
Wiki | Non-coding | Xia Xueying | 05/06/2015 | 17/06/2015 |
Research technical knowledge | Non-coding | All team member | 01/06/2015 | 17/06/2015 |
UI mock-up | Non-coding | Wang Yiyi | 10/06/2015 | 17/06/2015 |
Set up SVN | Non-coding | All team member | 16/06/2015 | 17/06/2015 |
Metrics | Non-coding | Xia Xueying | 16/06/2015 | 17/06/2015 |
Iteration 2
18 June – 24 June
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
Login/Logout | Coding | Gao Yiming | 18/06/2015 | 19/06/2015 |
Registration | Coding | Gao Yiming | 19/06/2015 | 20/06/2015 |
Test Cases | Non-coding | Zhang Jiahang | 21/06/2015 | 22/06/2015 |
integration& debug | Coding | Cao Xinge | 21/06/2015 | 24/06/2015 |
Iteration 3
25 June – 7 July
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
Push deals | Coding | Cao Xinge | 25/06/2015 | 27/06/2015 |
Withdraw deals | Coding | Cao Xinge | 27/06/2015 | 01/07/2015 |
Update restaurant profile | Coding | Cao Xinge | 01/07/2015 | 03/07/2015 |
Update preference | Coding | Zhang Jiahang | 25/06/2015 | 27/06/2015 |
View deals | Coding | Zhang Jiahang | 27/06/2015 | 03/07/2015 |
Preview deals | Coding | Gao Yiming | 25/06/2015 | 27/06/2015 |
Generate confirmation ID | Coding | Gao Yiming | 27/06/2015 | 03/07/2015 |
Test Cases | Non-coding | Xia Xueying | 05/07/2015 | 05/07/2015 |
Integration& Debugging | Coding | Gao Yiming | 05/07/2015 | 05/07/2015 |
Deploy | Non-coding | Zhang Jiahang | 05/07/2015 | 06/07/2015 |
Iteration 4
8 July – 21 July
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
finish updating Wiki Page | Non-coding | Xia xueying | 08/07/2015 | 14/07/2015 |
Mock up for front page | Non-coding | All team member | 08/07/2015 | 08/07/2015 |
Start coding UI for existing functions | Coding | Wang Yiyi | 09/07/2015 | 18/07/2015 |
Verify ID(Merchant) | Coding | Gao Yiming | 13/07/2015 | 16/07/2015 |
View favourite restaurant(Merchant) | Coding | Cao Xinge | 10/07/2015 | 13/07/2015 |
Make reservation(Customer) | Coding | Gao Yiming | 08/07/2015 | 13/07/2015 |
Like restaurant(Customer) | Coding | Cao Xinge | 08/07/2015 | 10/07/2015 |
Retrieve and convert Location and calculate distance | Coding | Zhang Jiahang | 08/07/2015 | 17/07/2015 |
View favorite restaurant(Customer) | Coding | Cao Xinge | 13/07/2015 | 16/07/2015 |
Update Last visited info | Coding | Gao Yiming | 09/07/2015 | 12/07/2015 |
Test & Debug | Coding | Xia Xueying, Wang Yiyi | 19/07/2015 | 21/07/2015 |
Deploy to server | Non-coding | All team member | 21/07/2015 | 21/07/2015 |
Iteration 5
22 July – 4 Aug
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take record on schedule | Non-coding | Xia Xueying | 22/07/2015 | 04/08/2015 |
prepare for supervisor meeting | Non-coding | Xia Xueying | 22/07/2015 | 24/07/2015 |
UI for login, merchant home, push deals, company profile | Coding | Wang Yiyi | 22/07/2015 | 25/07/2015 |
UI for reservation, customer main page | Coding | Wang Yiyi | 26/07/2015 | 01/08/2015 |
recommendation (favorite list) | Coding | Gao Yiming | 22/07/2015 | 25/07/2015 |
recommendation (budget) | Coding | Gao Yiming | 25/07/2015 | 28/07/2015 |
recommendation (cuisine type) | Coding | Gao Yiming | 28/07/2015 | 01/08/2015 |
push notification | Coding | Cao Xinge | 22/07/2015 | 25/07/2015 |
push similar deal | Coding | Gao Yiming | 01/08/2015 | 01/08/2015 |
Customer to deal travel distance | Coding | Zhang Jiahang | 22/07/2015 | 25/07/2015 |
Code Optimization | Coding | Zhang Jiahang | 01/08/2015 | 02/08/2015 |
test case | Non-coding | Xia Xueying | 01/08/2015 | 02/08/2015 |
Test & Debug | Non-coding | Xia Xueying, Wang Yiyi | 03/08/2015 | 03/08/2015 |
Deploy to server | Non-coding | All team member | 04/08/2015 | 04/08/2015 |
Iteration 6
5 August – 17 August
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
prepare slides | Non-coding | Xia Xueying | 05/08/2015 | 12/08/2015 |
Prepare UAT | Non-coding | All Team Member | 06/08/2015 | 11/08/2015 |
UAT1 | Non-coding | All Team Member | 12/08/2015 | 13/08/2015 |
UI adjustment | Coding | Wang Yiyi | 14/08/2015 | 15/08/2015 |
Testing & Debugging | Coding | Gao Yiming | 14/08/2015 | 15/08/2015 |
Deploy | Non-coding | Cao Xinge | 16/08/2015 | 17/08/2015 |
Iteration 7
18 August – 30 August
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-coding | Xia Xueying | 27/08/2015 | 27/08/2015 |
prepare for supervisor meeting | Non-coding | Xia Xueying | 27/08/2015 | 27/08/2015 |
UAT1 | Update UI for UAT1 | Wang Yiyi | 18/08/2015 | 30/08/2015 |
Update DB | Coding | Gao Yiming, Zhang Jiahang | 18/08/2015 | 20/08/2015 |
View deals status | Coding | Gao Yiming | 18/08/2015 | 20/08/2015 |
Deal template | Coding | Zhang Jiahang | 25/08/2015 | 28/08/2015 |
send user email to confirm the registration | Coding | Zhang Jiahang | 20/08/2015 | 21/08/2015 |
redemption history for merchant | Coding | Zhang Jiahang | 22/08/2015 | 24/08/2015 |
Test Case | Non-Coding | Xia Xueying | 25/08/2015 | 27/08/2015 |
Testing & Debugging | Coding | Gao Yiming | 14/08/2015 | 15/08/2015 |
Deploy | Non-coding | Cao Xinge | 16/08/2015 | 17/08/2015 |
Iteration 8
31 August – 14 September
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-coding | Xia Xueying | 31/08/2015 | 02/09/2015 |
Prepare UAT2 | Non-coding | Xia Xueying | 31/08/2015 | 02/09/2015 |
update UI for UAT | Coding | Wang Yiyi | 31/08/2015 | 11/08/2015 |
Withdraw deals(handle user withdraw after ding) | Coding | Gao Yiming | 31/08/2015 | 02/09/2015 |
Deal expiration + number restriction | Coding | Zhang Jiahang | 31/08/2015 | 02/09/2015 |
UAT improve | Coding | Cao Xinge | 31/08/2015 | 11/09/2015 |
Test Case | Non-Coding | Xia Xueying | 12/09/2015 | 12/09/2015 |
Testing & Debugging | Coding | All Team Member | 13/09/2015 | 13/09/2015 |
Deploy | Non-coding | All Team Member | 14/09/2015 | 14/09/2015 |
Iteration 9
15 September - 28 September
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-coding | Xia Xueying | 15/09/2015 | 16/09/2015 |
UAT2 | Non-coding | All Team Member | 17/09/2015 | 20/09/2015 |
gather UAT feedback | Non-coding | Xia Xueying | 20/09/2015 | 20/09/2015 |
change UI | Coding | Wang Yiyi | 20/09/2015 | 27/09/2015 |
reset password | Coding | Zhang Jiahang | 20/09/2015 | 21/09/2015 |
confirmation email content | Coding | Zhang Jiahang | 21/09/2015 | 22/09/2015 |
separate code | Coding | Gao Yiming | 20/09/2015 | 20/09/2015 |
deal start time | Coding | Zhang Jiahang | 21/09/2015 | 22/09/2015 |
shorten the redemption step | Coding | Gao Yiming | 21/09/2015 | 22/09/2015 |
manage deal template | Coding | Zhang Jiahang | 22/09/2015 | 24/09/2015 |
deal performance detail | Coding | Gao Yiming | 21/09/2015 | 22/09/2015 |
input validation javascript | Coding | Cao Xinge | 22/09/2015 | 24/09/2015 |
budget slider/distance slider | Coding | Gao Yiming | 22/09/2015 | 23/09/2015 |
like company ajex | Coding | Gao Yiming | 17/09/2015 | 20/09/2015 |
Test Case | Non-coding | Xia Xueying | 26/09/2015 | 26/09/2015 |
Testing & Debugging | Coding | All Team Members | 27/09/2015 | 27/09/2015 |
Deploy | Non-coding | All Team Members | 28/09/2015 | 28/09/2015 |
Iteration 10
29 September - 12 October
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-coding | Xia Xueying | 29/09/2015 | 29/09/2015 |
Prepare UAT3 | Non-coding | Xia Xueying | 29/09/2015 | 30/09/2015 |
improve UI | Coding | Wang Yiyi | 29/09/2015 | 02/10/2015 |
display restaurant list | Coding | Cao Xinge | 29/09/2015 | 01/10/2015 |
improve input field | Coding | Cao Xinge | 29/09/2015 | 02/10/2015 |
improve function | Coding | Gao Yiming | 29/09/2015 | 02/10/2015 |
UAT3 | Non-coding | All Team Member | 03/10/2015 | 03/10/2015 |
gather UAT3 feedback | Non-coding | Xia Xueying | 03/10/2015 | 03/10/2015 |
UI Changes | Coding | Wang Yiyi | 03/10/2015 | 06/10/2015 |
function changes | Coding | Gao Yiming | 03/10/2015 | 05/10/2015 |
midterm preparation | Non-coding | Xia Xueying | 03/10/2015 | 07/10/2015 |
midterm presentation | Non-coding | All Team Members | 09/10/2015 | 09/10/2015 |
midterm feedback gathering | Non-coding | Xia Xueying | 09/10/2015 | 09/10/2015 |
function changes | Coding | Gao Yiming | 10/10/2015 | 10/10/2015 |
Test Case | Non-coding | Xia Xueying | 10/10/2015 | 10/10/2015 |
Testing & Debugging | Coding | All Team Members | 11/10/2015 | 12/10/2015 |
Deploy | Non-coding | All Team Members | 12/10/2015 | 12/10/2015 |
Iteration 11
Oct 13 - Oct 26
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-coding | Xia Xueying | 13/10/2015 | 13/10/2015 |
Share deal with friends (Whatsapp, Facebook) | Coding | Zhang Jiahang | 13/10/2015 | 15/10/2015 |
Make change on deal detail page | Coding | Gao Yiming | 13/10/2015 | 16/10/2015 |
Make change on deal confirmation page | Coding | Cao Xinge | 13/10/2015 | 16/10/2015 |
Test Cases | Non-coding | Xia Xueying | 20/10/2015 | 20/10/2015 |
integration & debug | Coding | All team members | 21/10/2015 | 25/10/2015 |
Deploy to server | Non-Coding | Cao Xinge | 25/10/2015 | 26/10/2015 |
Iteration 12
Oct 27 - Nov 9
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take record on schedule | Non-coding | Xia Xueying | 27/10/2015 | 27/10/2015 |
Generate Report (analyse reach, view, ding for a deal) | Coding | Gao Yiming | 27/10/2015 | 31/10/2015 |
generate PDF | Coding | Zhang Jiahang | 27/10/2015 | 28/10/2015 |
Scan QR code to redeem | Coding | Zhang Jiahang | 28/10/2015 | 29/10/2015 |
Make change on push deal function | Coding | Zhang Jiahang | 31/10/2015 | 01/11/2015 |
Review | Coding | Cao Xinge | 01/11/2015 | 03/11/2015 |
DB change | Coding | Cao Xinge, Gao Yiming | 28/10/2015 | 30/10/2015 |
Video & Poster | Non-coding | Xia Xueying | 28/10/2015 | 31/10/2015 |
Finalize UI | Non-coding | Wang Yiyi | 01/11/2015 | 03/11/2015 |
Test Cases | Non-coding | Xia Xueying | 04/11/2015 | 04/11/2015 |
integration& debug | Coding | Cao Xinge | 05/11/2015 | 07/11/2015 |
Deploy | Non-Coding | Cao Xinge | 08/11/2015 | 08/11/2015 |
Iteration 13
Nov 10 - Nov 24
Function | Category | Assign to | Date Scheduled | Date Completed |
---|---|---|---|---|
take recored on schedule | Non-Coding | Xia Xueying | 10/11/2015 | 10/11/2015 |
Prepare for UAT4 | Non-Coding | Xia Xueying | 11/11/2015 | 11/11/2015 |
UAT for students | Non-Coding | All | 16/11/2015 | 16/11/2015 |
Gather feedback | Non-Coding | Xia Xueying | 16/11/2015 | 16/11/2015 |
Debug | Coding | Gao Yiming | 19/06/2015 | 20/06/2015 |
UAT for Merchants | Non-Coding | All | 19/11/2015 | 19/11/2015 |
Test Cases | Non-coding | Xia Xueying | 20/11/2015 | 20/11/2015 |
prepare for final presentation | Non-coding | Xia Xueying | 20/11/2015 | 20/11/2015 |
integration& debug | Coding | Cao Xinge | 21/11/2015 | 22/11/2015 |
Deploy | Non-coding | Gao Yiming | 22/11/2015 | 22/11/2015 |