IS480 Team wiki: 2015T1 Team Big Hero 5 Metrics
Revision as of 11:40, 15 August 2015 by Xyxia.2013 (talk | contribs)
Schedule | Metrics | Task List |
---|
Schedule Metrics
Iterations
Iteration | Planned Days | Actual Days | Score | Actions Taken |
---|---|---|---|---|
0 | 29 | 29 | 100% | None. We are on schedule |
1 | 17 | 17 | 100% | None. We are on schedule |
2 | 7 | 7 | 100% | None. We are on schedule |
3 | 13 | 13 | 100% | None. We are on schedule |
4 | 14 | 14 | 100% | None. We are on schedule |
5 | 14 | 14 | 100% | None. We are on schedule |
6 | 13 | 13 | 100% | None. We are on schedule |
7 | 14 | |||
8 | ||||
9 | ||||
10 | ||||
11 | ||||
12 | ||||
13 |
Bug Metrics
Iterations
Iteration | Low | High | Critical | Total Score | Actions Taken |
---|---|---|---|---|---|
2 | 0 | 3 | 0 | 15 | Use scheduled debugging time for debugging |
3 | 0 | 0 | 1 | 10 | Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled |
4 | 1 | 0 | 1 | 11 | Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled |
5 |