Schedule Metrics Task List

Schedule Metrics


SMplan.png


Sm.png


Bh5finalworkinghours.png

Iterations

Iteration Planned Tasks Actual Tasks Score Actions Taken
0 2 2 100% None. We are on schedule
1 7 7 100% None. We are on schedule
2 4 4 100% None. We are on schedule
3 10 10 100% None. We are on schedule
4 12 12 100% None. We are on schedule
5 15 15 100% None. We are on schedule
6 6 6 100% None. We are on schedule
7 13 11 118% 1. PM to find out the cause of delay from developers 2. Re-estimate the tasks for future iterations 3. Allocate more time for similar functionalities 4. Increase programming sessions for next iteration
8 9 9 100% None. We are on schedule
9 17 17 100% None. We are on schedule
10 17 17 100% None. We are on schedule
11 10 8 125% 1. Emergency team meeting 2.PM to find out the cause of delay from developers 2. Re-estimate the tasks for future iterations 3. Allocate more time for similar functionalities 4. Increase programming sessions for next iteration
12 11 11 100% None. We are on schedule
13 9 9 100% None. We are on schedule

Bug Metrics


BMplan.png


Bh5finalBM.png

Iterations

Iteration Low High Critical Total Score Actions Taken
2 0 3 0 15 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled
3 0 0 1 10 Use scheduled debugging time for debugging
4 1 0 1 11 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled
5 0 0 1 10 Use scheduled debugging time for debugging
6 0 0 1 10 Use scheduled debugging time for debugging
7 1 1 3 36 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled
8 0 3 1 25 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled
9 2 5 0 27 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled
10 0 0 1 10 Use scheduled debugging time for debugging
11 3 0 0 3 Use scheduled debugging time for debugging
12 2 1 0 7 Use scheduled debugging time for debugging
13 2 3 0 17 Stop current development and resolve the bug immediately. However, as we completed the functionalities early, we managed to solve the bugs before the end of iteration. Hence, project was not rescheduled