Task Metric
Task Metric Score & Description
Sprint | Estimated No. of Hours | Actual No. of Hours | Metric Score | Description |
---|---|---|---|---|
0 | 50 | 50 | 1.00 | Accurate estimation of tasks |
1 | 40 | 40 | 1.00 | Accurate estimation of tasks |
2 | 41 | 37.5 | 1.09 | Estimation of tasks is fairly accurate and did not affect the project schedule. |
3 | 54.5 | 55 | 0.99 | Estimation of tasks is fairly accurate and did not affect the project schedule. |
4 | 39 | 40.5 | 0.96 | Estimation of tasks is fairly accurate and did not affect the project schedule. |
5 | 104 | 98.75 | 1.05 | Estimation of tasks is fairly accurate and did not affect the project schedule. |
6 | 67 | 56 | 1.20 | Estimation of tasks is not as accurate as planned. There is an over-estimation of time required to completed some of the tasks. |
7 | 69.5 | 60 | 1.16 | Estimation of tasks is not as accurate as planned. There is an over-estimation of time required to completed some of the tasks. |
8 | 81.5 | 80.5 | 1.01 | Estimation of tasks is fairly accurate and did not affect the project schedule. |