IS480 Team wiki: 2015T1 4Sight Task Metrics
Revision as of 15:15, 5 October 2015 by Amabel.lau.2012 (talk | contribs) (→Tasks Breakdown by Sprint)
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Project Schedule | Software Development Methodologies | Schedule Metrics | Task Metrics | Bug Metrics | Risk Management | Change Management |
Task Metric
Task Metric Score & Description
Sprint | Estimated No. of Hours | Actual No. of Hours | Metric Score | Description |
---|---|---|---|---|
0 | 50 | 50 | 1.00 | Accurate estimation of tasks |
1 | 40 | 40 | 1.00 | Accurate estimation of tasks |
2 | 41 | 37.5 | 1.09 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |
3 | 54.5 | 55 | 0.99 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |
4 | 39 | 40.5 | 0.96 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |
5 | 104 | 98.75 | 1.05 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |
6 | 67 | 56 | 1.20 | Estimation of tasks is not as accurate as planned. There is an over-estimation of time required to complete some of the tasks. These include tasks for the designing of the admin page and some of the angular interactions between the frontend and backend when implementing the manage account feature for the administrative module. |
7 | 69.5 | 60 | 1.16 | Estimation of tasks is not as accurate as planned. There is an over-estimation of time required to complete tasks related to the survey feature of the notification module due to some changes requested from the sponsor. |
8 | 81.5 | 80.5 | 1.01 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |
9 | 40.0 | 36.5 | 1.10 | Estimation of tasks is fairly accurate. Project schedule is not affected, proceed as planned. |