HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2015T1 4Sight Task Metrics"

From IS480
Jump to navigation Jump to search
Line 126: Line 126:
 
| style="text-align:center" | 1.16
 
| style="text-align:center" | 1.16
 
| style="text-align:center" | Estimation of tasks is not as accurate as planned.<br> There is an over-estimation of time required to completed some of the tasks.  
 
| style="text-align:center" | Estimation of tasks is not as accurate as planned.<br> There is an over-estimation of time required to completed some of the tasks.  
 +
 +
| style="text-align:center" | 5
 +
| style="text-align:center" | 81.5
 +
| style="text-align:center" | 80.5
 +
| style="text-align:center" | 1.01
 +
| style="text-align:center" | Estimation of tasks is fairly accurate and did not affect the project schedule.
 
|}
 
|}
 
</div>
 
</div>

Revision as of 12:34, 29 September 2015

4Sight team logo.png
4Sight Home.png HOME   4Sight Team.png ABOUT US   4Sight Project overview.png PROJECT OVERVIEW   4Sight Project management.png PROJECT MANAGEMENT   4Sight Documentation.png DOCUMENTATION  
Project Schedule Software Development Methodologies Schedule Metrics Task Metrics Bug Metrics Risk Management Change Management

Task Metric

4Sight TaskMetric.png

Schedule Metric Score & Description

4Sight TaskMetricScore.JPG
Sprint Estimated No. of Hours Actual No. of Hours Metric Score Description
0 50 50 1.00 Accurate estimation of tasks
1 40 40 1.00 Accurate estimation of tasks
2 41 37.5 1.09 Estimation of tasks is fairly accurate and did not affect the project schedule.
3 54.5 55 0.99 Estimation of tasks is fairly accurate and did not affect the project schedule.
4 39 40.5 0.96 Estimation of tasks is fairly accurate and did not affect the project schedule.
5 104 98.75 1.05 Estimation of tasks is fairly accurate and did not affect the project schedule.
6 67 56 1.20 Estimation of tasks is not as accurate as planned.
There is an over-estimation of time required to completed some of the tasks.
7 69.5 60 1.16 Estimation of tasks is not as accurate as planned.
There is an over-estimation of time required to completed some of the tasks.
5 81.5 80.5 1.01 Estimation of tasks is fairly accurate and did not affect the project schedule.

Tasks Breakdown by Sprint

Sprint 2 Tasks Breakdown
Sprint 3 Tasks Breakdown
Sprint 4 Tasks Breakdown
Sprint 5 Tasks Breakdown
Sprint 6 Tasks Breakdown
Sprint 7 Tasks Breakdown
Sprint 8 Tasks Breakdown