Difference between revisions of "IS480 Team wiki: 2015T1 4Sight Change Management"
Jump to navigation
Jump to search
Line 252: | Line 252: | ||
| width=20% align=center|Accepting the request would not affect the project schedule | | width=20% align=center|Accepting the request would not affect the project schedule | ||
| width=20% align=center | To add a new user story for this change request and to be scheduled in subsequent sprint | | width=20% align=center | To add a new user story for this change request and to be scheduled in subsequent sprint | ||
− | | width=5% align=center | | + | | width=5% align=center | Completed |
|- | |- | ||
Line 382: | Line 382: | ||
| width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | | width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | ||
| width=20% align=center |No change to project scope. Slight modication of project schedule to include the enhancement of suggestion of appointment time slot feature. | | width=20% align=center |No change to project scope. Slight modication of project schedule to include the enhancement of suggestion of appointment time slot feature. | ||
− | | width=5% align=center | | + | | width=5% align=center | Completed |
|- | |- | ||
Line 395: | Line 395: | ||
| width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | | width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | ||
| width=20% align=center |Added feature to project scope and timeline | | width=20% align=center |Added feature to project scope and timeline | ||
− | | width=5% align=center | | + | | width=5% align=center | Completed |
|- | |- | ||
Line 408: | Line 408: | ||
| width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | | width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 20. | ||
| width=20% align=center |Added feature to project scope and timeline | | width=20% align=center |Added feature to project scope and timeline | ||
− | | width=5% align=center | | + | | width=5% align=center | Completed |
|} | |} | ||
</div> | </div> |
Latest revision as of 20:37, 27 November 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Project Schedule | Software Development Methodologies | Schedule Metrics | Task Metrics | Bug Metrics | Risk Management | Change Management |
Change Management Process
|
|