Line 396: | Line 396: | ||
| width=20% align=center |Added feature to project scope and timeline | | width=20% align=center |Added feature to project scope and timeline | ||
| width=5% align=center | In Progress | | width=5% align=center | In Progress | ||
+ | |||
+ | |- | ||
+ | | width=3% align=center |23 | ||
+ | | width=3% align=center| 11 | ||
+ | | width=5% align=center | 24/10/2015 | ||
+ | | width=10% align=center |Remove mobile calendar module | ||
+ | | width=25% align=center | | ||
+ | | width=10% align=center|Visual representations and simple manipulation of data | ||
+ | | width=3% align=center | 3 | ||
+ | | width=5% align=center | Accept | ||
+ | | width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 18. | ||
+ | | width=20% align=center |Added feature to project scope and timeline | ||
+ | | width=5% align=center | Completed | ||
|} | |} | ||
</div> | </div> |
Revision as of 21:14, 10 November 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Project Schedule | Software Development Methodologies | Schedule Metrics | Task Metrics | Bug Metrics | Risk Management | Change Management |
Change Management Process
|
|