| width=5% align=center | 24/10/2015 | | width=5% align=center | 24/10/2015 | ||
| width=10% align=center |Forecast appointment slots availability based on historical data | | width=10% align=center |Forecast appointment slots availability based on historical data | ||
− | | width=25% align=center |In our discussion on how to make the application more intelligent, our team proposed on | + | | width=25% align=center |In our discussion on how to make the application more intelligent, our team proposed to improve on the existing suggestion of appointment time slot feature. Instead of just listing the next earliest available time slot, we suggested to do a forecast of appointment time slots availability based on historical data (previous months appointment schedule). This means that the availability of a particular time slot is not based on the existing number of patients in that time slot (heatmap visualization) but are inferred based on historical data of appointments that were previously scheduled on the same day, time, appointment type and doctor. |
− | | width=10% align=center| | + | | width=10% align=center|Change the logic of existing suggestion of appointment time slot feature |
| width=3% align=center | 3 | | width=3% align=center | 3 | ||
| width=5% align=center | Accept | | width=5% align=center | Accept | ||
| width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 18. | | width=20% align=center|Accepting this request will not affect the project schedule. Team will be using the 2 weeks development cost saved as mentioned in change request 18. | ||
− | | width=20% align=center | | + | | width=20% align=center |No change to project scope. Slight modication of project schedule to include the enhancement of suggestion of appointment time slot feature. |
| width=5% align=center | In Progress | | width=5% align=center | In Progress | ||
Revision as of 21:12, 10 November 2015
HOME | ABOUT US | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION |
Project Schedule | Software Development Methodologies | Schedule Metrics | Task Metrics | Bug Metrics | Risk Management | Change Management |
Change Management Process
|
|