IS480 Team wiki: 2014T1 Team Xcellence Final
Revision as of 00:20, 18 November 2014 by Andy.teng.2011 (talk | contribs)
Project Progress Summary
Visit the live deployed site at:
- myCSISG Web Portal: http://www.mycsisg.org/nextgen/
- myCSISG Survey App: http://www.mycsisg.org/SurveyApp/
- Please contact SMU ISES for access to the sites.
Visit our staging site with various login credentials:
- myCSISG Web Portal: http://54.179.141.102/mycsisg/
- Client:
- Username: TeamXcellence
- Password: 123
- Note: If you create a project, please email andy.teng.2011@sis.smu.edu.sg to forward you the generated email containing project details.
- Admin:
- Username: admin
- Password: 123
- Client:
- myCSISG Survey App: http://54.179.141.102/SurveyApp
- Surveyor Admin:
- Username: <to-be released later>
- Password: <to-be released later>
- Surveyor:
- Username: <to-be released later>
- Password: <to-be released later>
- Surveyor Admin:
Project Highlights:
- highlights
Project Challenges:
- challenges
Project Achievements:
- achievements
Project Management
Project Status:
- status
Project Schedule (Plan Vs Actual):
For summary of Plan Vs Actual per iteration before mid-terms, please refer to here.
Summary of Plan Vs Actual per iteration (after mid-terms):
- Iteration 8
- ...
- Iteration 9
- ...
- Iteration 10
- ...
- Iteration 11
- ...
- Iteration 12
- ...
Click to view our project timeline overview
Project Metrics:
Click to view our Schedule and Bug metrics
- Note: Data collection for bug metrics only started in iteration 3. This was because we started on development from iteration 3 onwards.
Technical Complexity:
...
Quality of product
Intermediate Deliverables:
Stage | Specification | Modules |
Project Management | Minutes | Internal & Sponsor & Supervisor Minutes |
Metrics | Schedule & Bug Metrics | |
Requirements | Personas & Scenarios | Personas & Scenarios |
Prototype | Low-Fi Prototype | |
Business requirements | Project Overview | |
Project scope | Project Scope | |
Analysis and Design | Use case | Use Case Diagram & Use Case Description |
ER Diagram | ER Diagram | |
Architecture Diagram | Architecture Diagram | |
Flow Diagram | Flow Diagram | |
Testing | UAT 1 | UAT 1 |
UAT 2 | UAT 2 | |
A|B Test Experiment | A|B Test Experiment | |
Load Test | Load Test | |
Handover | Manuals | User tutorial, Deployment manual |
Code | client server |
Deployment:
Visit the live deployed site at:
- myCSISG Web Portal: http://www.mycsisg.org/nextgen/
- myCSISG Survey App: http://www.mycsisg.org/SurveyApp/
- Please contact SMU ISES for access to the sites.
Visit our staging site with various login credentials:
- myCSISG Web Portal: http://54.179.141.102/mycsisg/
- Client:
- Username: TeamXcellence
- Password: 123
- Note: If you create a project, please email andy.teng.2011@sis.smu.edu.sg to forward you the generated email containing project details.
- Admin:
- Username: admin
- Password: 123
- Client:
- myCSISG Survey App: http://54.179.141.102/SurveyApp
- Surveyor Admin:
- Username: <to-be released later>
- Password: <to-be released later>
- Surveyor:
- Username: <to-be released later>
- Password: <to-be released later>
- Surveyor Admin:
Testing:
We have conducted 2 User Acceptance Test, 1 A|B Test Experiment and 1 Load Test. Click here to view any of the tests information.
Here's a quick summary of each of the test conducted:
- UAT 1
- 10 real ISES clients kindly participated
- The objectives were to align ISES's expectation with our current product, better understand the real user's needs and identify areas to enhance their experience with myCSISG.
- View more about UAT 1 here
- UAT 2
- 6 real ISES clients kindly participated
- The objective was to understand if myCSISG web application and survey app is ready for commercial use by ISES clients
- View more about UAT 2 here
- A|B Test Experiment
- 30 participants are selected on the basis that they have done a survey within the last 3 months
- The objective was to determine which layout (Keypad vs Slider) will help surveyors be efficient and accurate
- View more about A|B Test Experiment here
- Load Test
- Load test was conducted on the live deployed site residing in ISES server
- The objective was to understand the performance of the web application and survey app residing in ISES server. We will recommend ISES a set of changes to make to improve the performance since we do not have the permissions to make the necessary changes.
- View more about Load Test here
Reflection
Team Reflection:
...
Teng Rui Jie Andy Reflection:
...
Tan Si Yu Reflection:
...
Wong Wei Xiong Reflection:
...
Weng Xinyong Reflection:
...
Lek Guan Zhou Reflection:
...
Chua Zhen Ling Reflection:
...
Sponsor Comment:
...