Project Schedule

- Updated on 12 September 2014

Changes

  • Add "System Testing and Debugging", "System Improvement" to Iteration 9
  • Add "Assign role-based access" to Iteration 5
  • Add "Reuse existing documents in multiple programs"
  • Move "Email Module" from Iteration 6 to Iteration 7
  • Move "Account Module" from Iteration 7 to Iteration 6
  • Remove "Role-based authorization for parents" from iteration 5
  • Extend Iteration 9: 12 Nov - 25 Nov (previously: 12 Nov - 30 Nov)


Pentagon Schedule v5.png



Check our archived schedule




Change Log

S/N Change Event Category Requester Priority Impact Level
1 Change the name from "Notification Email" to "Automatic Email Notification" Modify functionality name Team Low No Impact
2 Add "View list of Application" to Iteration 3 Add functionality Sponsor Medium Medium
3 Move "Accept Application" from Iteration 3 to Iteration 4 Move functionality Team Low Low
4 Move "Withdraw from Program" from Iteration 3 to Iteration 5 Move functionality Team Low Low
5 Move "CRUD email templates" from iteraion 4 to iteration 5 Move functionality Team Low Low
6 Add "Search Program" to Iteration 5 Add functionality Sponsor Medium Low
7 Remove "Create, View Program Page Template" from Iteration 5 Remove functionality Sponsor Low No Impact
8 Remove "Update Program Page Template" from Iteration 6 Remove functionality Sponsor Low No Impact
9 Move "Track Application Progress" from Iteration 5 to Iteration 6 Move functionality Sponsor Medium Medium
10 Add "Custom Email for Stakeholders" to Iteration 6 Add functionality Sponsor Low High
11 Move "Track Application Progress" from Iteration 5 to Iteration 6 Add functionality Sponsor Medium Medium
12 Add "Archive Program" to Iteration 2 Add functionality Team Medium Low
13 Move "Update, Delete Program" from Iteration 3 to Iteration 2 Move functionality Team Low Low
14 Move "Search Program" from Iteration 3 to Iteration 2 Move functionality Team Low Low
15 Add "Appy to Program" to Iteration 2 Add functionality Sponsor High High
16 Move "View list of application" from Iteration 3 to Iteration 2 Move functionality Team Low Low
17 Remove "Delete Registration Form" from Iteration 4 Move functionality Sponsor Low No Impact
18 Move "Accept Application", "Reject Application" from Iteration 4 to Iteration 3 Move functionality Team Medium High
19 Move "Withdraw from Program" from Iteration 5 to Iteration 3 Move functionality Team Medium High
20 Move "Track Application Progress" from Iteration 6 to Iteration 3 Move functionality Sponsor Medium High
21 Move "Delete Documents" from Iteration 4 to Iteration 3 Move functionality Team Low Low
22 Add "Download Documents" to Iteration 3 Add functionality Sponsor High Medium
23 Add "Send Automatic Emaill at Application Status Change" to Iteration 4 Move functionality Sponsor High High
24 Move "Auto-Schedule Email" from Iteration 7 to Iteration 4 Move functionality Sponsor Low High
25 Add "Role-based Authorization for Teachers" from Iteration 7 to Iteration 4 Add functionality Sponsor High High
26 Move "Login/Logout (Facebook)" from Iteration 4 to Iteration 5 Move functionality Team Low Low
27 Move "Administratior Dashboard" from Iteration 7 to Iteration 5 Move functionality Sponsor Low Low
28 Move "Upload Document" from Iteration 4 to Iteration 2 Move functionality Team Medium Low
29 Move "Read Document" from Iteration 4 to Iteration 5 Move functionality Sponsor Medium Medium
30 Move "Export selective participant data" from Iteration 7 to Iteration 5 Move functionality Sponsor High High
31 Add "View List of documents by Program" to Iteration 5 Add functionality Sponsor Low Low
32 Move "CRUD email Templates" from Iteration 7 to Iteration 6 Move functionality Team Low Low
33 Add "Analyze Participant Data", "Analyze Program Data" to Iteration 7 Add functionality Team Low Medium
34 Move "Release of version 0.3" from Iteration 8 to Iteration 6 Move functionality Team Medium Low
35 Shift "User Testing #1" from 30 Jul to 05 Aug Shift milestone Sponsor Medium Low
36 Shift "User Testing #2" from 27 Sep to 22 Sep Shift milestone Sponsor Medium Low
37 Add "User Testing #3" on 14 Oct Add milestone Team Medium Medium
38 Shift "User Testing #4" from 17 Nov to 10 Nov Shift milestone Team Low Low
39 Add "Go Live #1" on 29 Sep Add milestone Supervisor High Medium
40 Add "Go Live #2" on 16 Nov Add milestone Supervisor High Medium
41 Shift "Mid-term Presentation" from 3 Oct to 9 Oct Shift milestone NA High Low
42 Shift "Final Presentation" from 28 Nov to 29 Nov Shift milestone NA High Low
43 Shift "Poster Submission" from 12 Nov to 10 Nov Shift milestone NA High Low
44 Shift "Poster Day" from 06 Dec to 03 Dec Shift milestone NA High Low
45 Shift Midterm Date from 09 Nov to 10 Nov Shift milestone NA High Low
46 Shift " User Testing #4" from 14 Nov to 16 Nov Shift milestone Team Medium Low
47 Shift "Go Live #2" from 23 Nov to 25 Nov Shift milestone Team Medium Medium
48 Extend Iteration 9: 12 Nov - 25 Nov (previously: 12 Nov - 30 Nov) Extend iteration Team Medium High
49 Add "System Testing and Debugging", "System Improvement" to Iteration 9 Add functionality Team Medium High
50 Move "Email Module" from Iteration 6 to Iteration 7 Move functionality Sponsor Low Low
51 Move "Account Module" from Iteration 7 to Iteration 6 Move functionality Sponsor Low Low
52 Shift "User Testing #4" from 17 Nov to 10 Nov Add functionality Sponsor High High
53 Remove "Role-based authorization for parents" from iteration 5 Remove functionality Sponsor Low Low
54 Add "Reuse existing documents in multiple programs" Add functionality Sponsor Medium High




Project Schdeule Simplified Version

Pentagon Schedule simplified.jpg