+ | == Usability Testing 1 == | ||
+ | |||
+ | <b>Planned Date:</b> 29th August 2014 | ||
+ | |||
+ | <b>Actual Date:</b> 28th August 2014 - 1st September 2014 | ||
+ | |||
+ | UT1 was conducted over a period of five days as some participants were not free and we can only conduct UT1 based on their available schedule. | ||
+ | |||
+ | === Purpose === | ||
+ | |||
+ | The purpose of UT1 is to test the functionalities that are already coded out, and gather feedback on what the users think of the current user interface design. | ||
+ | |||
+ | === Scope === | ||
+ | |||
+ | The functions tested out in UT 1 on iOS are: | ||
+ | |||
+ | #Registration | ||
+ | #Login | ||
+ | #Display All Feedback (Listing) | ||
+ | #Submit Basic Feedback (excludes multiple images and annotation) | ||
+ | # | ||
+ | |||
+ | === Results === | ||
+ | |||
+ | == Usability Testing 2 == | ||
+ | |||
+ | Date: 10th October 2014 (Tentatively Scheduled) | ||
+ | |||
+ | Proposed Date Change: 10th October 2014 - 17th October 2014 (to cater to participant's schedule) | ||
+ | |||
+ | === Purpose === | ||
+ | |||
+ | === Scope === | ||
+ | |||
+ | === Results === |
Revision as of 16:57, 27 September 2014
Home | Project Overview | Project Management | Documentation | Team |
Design Overview | Prototype | User Testing | Meeting Minutes | Submission Archive |
Contents
Usability Testing 1
Planned Date: 29th August 2014
Actual Date: 28th August 2014 - 1st September 2014
UT1 was conducted over a period of five days as some participants were not free and we can only conduct UT1 based on their available schedule.
Purpose
The purpose of UT1 is to test the functionalities that are already coded out, and gather feedback on what the users think of the current user interface design.
Scope
The functions tested out in UT 1 on iOS are:
- Registration
- Login
- Display All Feedback (Listing)
- Submit Basic Feedback (excludes multiple images and annotation)
Results
Usability Testing 2
Date: 10th October 2014 (Tentatively Scheduled)
Proposed Date Change: 10th October 2014 - 17th October 2014 (to cater to participant's schedule)