Line 44: Line 44:
  
 
[[Image: Story_Burn_Up_Chart_Epsilon.png|800px]]
 
[[Image: Story_Burn_Up_Chart_Epsilon.png|800px]]
 +
 +
This burn up chart tracks how much work has been completed and the total amount of work done by the team.
 +
 +
For more information, please check out our [https://wiki.smu.edu.sg/is480/IS480_Team_wiki%3A_2014T1_Team_Epsilon_Project_Management Methodology] section.
  
 
== '''Schedule Metrics''' ==
 
== '''Schedule Metrics''' ==

Revision as of 17:13, 6 October 2014

Team Epsilon Logo.png.png

Home   Project Overview   Project Management   Documentation   Team

Methodology   Project Schedule   Metrics Management   Risk Management


Story Burn Up Chart

Story Burn Up Chart Epsilon.png

This burn up chart tracks how much work has been completed and the total amount of work done by the team.

For more information, please check out our Methodology section.

Schedule Metrics

Absolute Days Delayed

Absolute Days Delayed Epsilon.png


If stories cannot be completed on time, they will either be:

  • scheduled to be done in the next iteration (timebox) OR
  • be developed by extending the current iteration

The decision will be based on the progress of the story as well as if there are any milestones that need to be met.


Schedule Index Guide

Schedule Index Guide Epsilon.png

Schedule Index

Schedule Index Epsilon.png

Schedule Index Chart Epsilon.png

Effort Metrics

Epsilon Effort Metric Latest.jpg

Bug Metrics

Severity Description
Low Impact
(1 point)
Unimportant. Typo error or small user interface alignment issues.
High Impact
(5 points)
The system runs. However, some non-critical functionalities are not working.
Critical Impact
(10 points)
The system is down or is un-usable after a short period of time. We have to fix the bugs to continue.
Bug Points* Action
< 10 Use the planned debugging time in the iteration.
>= 10 Stop current development and resolve the bugs immediately. Project Manager reschedules the project.

* Bug Points = (# Low Impact Bugs) + 5(# High Impact Bugs) + 10(# Critical Impact Bugs)


Epsilon Midterm Bug Metric.png

Risk Metrics