IS480 Team wiki: 2014T1 Happy Sounds Bug Metrics
Revision as of 00:40, 14 August 2014 by Qiyang.tan.2012 (talk | contribs)
HOME | PROJECT OVERVIEW | PROJECT MANAGEMENT | DOCUMENTATION | ABOUT US |
PROJECT SCHEDULE | METHODOLOGY | METRICS MANAGEMENT | RISK MANAGEMENT | MEETING MINUTES |
SCHEDULE METRICS | BUG METRICS |
---|
Severity | Description |
---|---|
Low Impact (1 point) |
Unimportant. Typo error or small user interface alignment issues. |
High Impact (5 point) |
The system runs. However, some non-critical functionalities are not working. |
Critical Impact (10 point) |
The system is down. Stop current development and resolve the bug immediately. Project Manager reschedules the project. |
Calculation: BUG SCORE = (1* No of Low Impact Bugs) + (5 * No of High Impact Bugs) + (10 * No of Critical Impact Bugs)
Bug Score | Action |
---|---|
Score<5 |
Fix during buffer time only |
5<=Score<10 |
Use planned debugging time |
10<=Score |
Stop current development and resolve the bug immediately. Project Manager reschedules the project. |