HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2013T2 OneRevolution ProjectManagement"

From IS480
Jump to navigation Jump to search
 
(8 intermediate revisions by 2 users not shown)
Line 30: Line 30:
 
| style="border-bottom:1px solid #232B2B; border-top:1px solid #2f2929; background:none;" width="1%" |  
 
| style="border-bottom:1px solid #232B2B; border-top:1px solid #2f2929; background:none;" width="1%" |  
 
| style="padding:0.4em; font-size:100%; background-color:#FFFFFF;  border-bottom:1px solid #2f2929; border-top:1px solid #2f2929; text-align:center; color:#232B2B" width="10%" | [[IS480_Team_wiki:_2013T2 OneRevolution ProjectManagement Metrics| <font face= "Tahoma" font color="#000000 "><b>Metrics</b></font>]]
 
| style="padding:0.4em; font-size:100%; background-color:#FFFFFF;  border-bottom:1px solid #2f2929; border-top:1px solid #2f2929; text-align:center; color:#232B2B" width="10%" | [[IS480_Team_wiki:_2013T2 OneRevolution ProjectManagement Metrics| <font face= "Tahoma" font color="#000000 "><b>Metrics</b></font>]]
 +
|}
  
|}
 
 
</p>
 
</p>
 +
 
[[Image:OneRevo-ProjectScheduleHeader1.png | 1100px]]
 
[[Image:OneRevo-ProjectScheduleHeader1.png | 1100px]]
<p>[[Image:OR metrics white.png | 1000px]]</p>
+
[[media:One_Revolution_Schedule.xlsx|Version 1 of schedule!]] <br/>
 +
[[media:OR Schedule Final.xlsx|Version 2 of schedule!]] <br/>
 +
<p>[[Image:OR milestone final.png | 1000px]]</p>
 
<br>
 
<br>
[[media:One_Revolution_Schedule.xlsx|View our detailed schedule here!]] <br/>
+
 
 
[[Image:OneRevo-ProjectScheduleHeader3.png | 1100px]]
 
[[Image:OneRevo-ProjectScheduleHeader3.png | 1100px]]
 
<br>
 
<br>
 
<br>
 
<br>
[[Image:OneRevoProcess.png | 700px]]
+
[[Image:OR planvsactual final.PNG | 700px]]<br>
 +
<br>
 +
</center>
 +
1. The first extension in iteration 3 is due to the issue with our Database Setup as our database was unable to connect to our server. It was taking much more time than expected which delayed our tasks, which was Saving Lane information into DB and display the Lane information from DB. This was due to the incompetency of the team towards Posgress SQL and Hiroku. Hence we decided to change the database (from Posgress SQL to mySQL) and server(from Hiroku to IS480 server) as time was limited to our acceptance date. This issue causes us to extend our iteration 3 for 4 days, 27th to 31st of October 2013 and change the start date of the 4th iteration to begin on 1st of November instead of 27th October 2013.<br><br>
 +
2. The second extension in iteration 5 is due to the bugs found in that iteration. It was in the critical zone hence the project manager reviewed the schedule and extended one day for debugging. This issue causes us to extend our iteration 5 for 1 day, 27th to 28th of December 2013 and change the start date of the 6th iteration to begin on 29th instead of 28th December 2013.

Latest revision as of 19:15, 16 April 2014

1234380 660420237315127 959544661 n.jpg

OneRevoHome.png Home   About Us 2.png About Us   OneRevoProjectOverview.png Project Overview   OneRevoProjectManagement.png Project Management   OneRevoProjectDocumentation.png Project Documentation

Project Schedule   Risks   Metrics

OneRevo-ProjectScheduleHeader1.png Version 1 of schedule!
Version 2 of schedule!

OR milestone final.png


OneRevo-ProjectScheduleHeader3.png

OR planvsactual final.PNG

1. The first extension in iteration 3 is due to the issue with our Database Setup as our database was unable to connect to our server. It was taking much more time than expected which delayed our tasks, which was Saving Lane information into DB and display the Lane information from DB. This was due to the incompetency of the team towards Posgress SQL and Hiroku. Hence we decided to change the database (from Posgress SQL to mySQL) and server(from Hiroku to IS480 server) as time was limited to our acceptance date. This issue causes us to extend our iteration 3 for 4 days, 27th to 31st of October 2013 and change the start date of the 4th iteration to begin on 1st of November instead of 27th October 2013.

2. The second extension in iteration 5 is due to the bugs found in that iteration. It was in the critical zone hence the project manager reviewed the schedule and extended one day for debugging. This issue causes us to extend our iteration 5 for 1 day, 27th to 28th of December 2013 and change the start date of the 6th iteration to begin on 29th instead of 28th December 2013.