Schedule Metrics
The Schedule Metrics(SM) is used to keep track on the progress of the team.
The result will be compiled and evaluated by the PM at the end of each iteration.
The table below states the action plan when the metric is within the range of scores
Schedule Metrics (SM) = Actual time/Estimated time
Score | Description | Action |
---|---|---|
SM > 1.3 |
Team is way behind schedule |
Very behind schedule. PM to conduct review to determine the cause of delay and to reschedule project. Consider dropping functionalities. |
1.1<=SM<=1.3 |
Team is behind schedule |
Behind schedule. PM to conduct review to determine the cause of delay. Bring delayed tasks into the next iteration and to reschedule project. Can choose to overload more tasks in the next iteration or push into buffer time |
0.9<=SM<=1.1 |
Team is on track |
Currently on track. Keep up with the progress. |
0.7=<SM<=0.9 |
Team is ahead of schedule |
Ahead of schedule. Review schedule and decide whether it is possible to bring forward tasks from next iteration to current iteration |
SM < 0.7 |
Team is way ahead of schedule |
Very ahead of schedule. Bring forward tasks from next iteration to current iteration. Reschedule remaining iterations. |
Bug Metrics
Severity | Description |
---|---|
Low Impact (1 points) |
Typo error or small user interface alignment issues |
High Impact (5 points) |
The application runs. However, some non-critical functionalities are not working |
Critical Impact(10 points) |
The application is down or is un-usable after a short period of time. The team must stop development and fix the bugs immediately |
Mitigation Plan
Points in Iteration | Action |
---|---|
Points < 10 |
Use the planned debugging time in the iteration |
Points >= 10 |
- Stop current development and resolve the bug immediately |