The Schedule Metrics(SM) is used to keep track on the progress of the team.<br?
+
The Schedule Metrics(SM) is used to keep track on the progress of the team.<br>
 
The result will be compiled and evaluated by the PM at the end of each iteration.<br>
 
The result will be compiled and evaluated by the PM at the end of each iteration.<br>
 
The table below states the action plan when the metric is within the range of scores <br><br>
 
The table below states the action plan when the metric is within the range of scores <br><br>

Revision as of 01:37, 26 October 2013

GENShYFT IS480 1314 Logo.jpg


Home   Project Overview   Project Management   Documentation   The Team


Overview   Risk   Schedule   Metric   Minutes


Schedule Metric


Genshyft is480 1314 metric1.JPG

Bug Metric


Genshyft is480 1314 metric2.JPG


Schedule Metrics

The Schedule Metrics(SM) is used to keep track on the progress of the team.
The result will be compiled and evaluated by the PM at the end of each iteration.
The table below states the action plan when the metric is within the range of scores

Schedule Metrics (SM) = Actual time/Estimated time

Score Description Action
SM > 1.3

Team is way behind schedule

Very behind schedule. PM to conduct review to determine the cause of delay and to reschedule project. Consider dropping functionalities.

1.1<=SM<=1.3

Team is behind schedule

Behind schedule. PM to conduct review to determine the cause of delay. Bring delayed tasks into the next iteration and to reschedule project. Can choose to overload more tasks in the next iteration or push into buffer time

0.9<=SM<=1.1

Team is on track

Currently on track. Keep up with the progress.

0.7=<SM<=0.9

Team is ahead of schedule

Ahead of schedule. Review schedule and decide whether it is possible to bring forward tasks from next iteration to current iteration

SM < 0.7

Team is way ahead of schedule

Very ahead of schedule. Bring forward tasks from next iteration to current iteration. Reschedule remaining iterations.