The Schedule Metrics(SM) is use to keep track on the progress of the team.
The objective of Schedule Metrics is to help the team to keep track of the progress of our project development.<br>
+
The result will be compiled and evaluated by the PM at the end of each iteration.<br>
The Schedule Metrics will be tracked by the Project Manager on per '''''Iteration basis'''''.<br><br>
+
'''''Schedule Metrics (SM) = Actual time/Estimated time '''''<br>
The following formula is used by the team to calculate Schedule Metrics (SM):<br>
 
'''''Schedule Metrics (SM) = Estimated time / Actual time'''''<br>
 
''*time is measured in Days''<br>
 
  
 
{|border="1" cellpadding="5" cellspacing="0" align="left" text-align="center"
 
{|border="1" cellpadding="5" cellspacing="0" align="left" text-align="center"

Revision as of 01:36, 26 October 2013

GENShYFT IS480 1314 Logo.jpg


Home   Project Overview   Project Management   Documentation   The Team


Overview   Risk   Schedule   Metric   Minutes


Schedule Metric


Genshyft is480 1314 metric1.JPG

Bug Metric


Genshyft is480 1314 metric2.JPG


Schedule Metrics

The Schedule Metrics(SM) is use to keep track on the progress of the team. The result will be compiled and evaluated by the PM at the end of each iteration.
Schedule Metrics (SM) = Actual time/Estimated time

Score Description Action
SM > 1.3

Team is way behind schedule

Very behind schedule. PM to conduct review to determine the cause of delay and to reschedule project. Consider dropping functionalities.

1.1<=SM<=1.3

Team is behind schedule

Behind schedule. PM to conduct review to determine the cause of delay. Bring delayed tasks into the next iteration and to reschedule project. Can choose to overload more tasks in the next iteration or push into buffer time

0.9<=SM<=1.1

Team is on track

Currently on track. Keep up with the progress.

0.7=<SM<=0.9

Team is ahead of schedule

Ahead of schedule. Review schedule and decide whether it is possible to bring forward tasks from next iteration to current iteration

SM < 0.7

Team is way ahead of schedule

Very ahead of schedule. Bring forward tasks from next iteration to current iteration. Reschedule remaining iterations.