HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2013T2 Excelente Final"

From IS480
Jump to navigation Jump to search
Line 246: Line 246:
  
 
====Individual Reflection====
 
====Individual Reflection====
[[Image:Excelente Noelle Reflection.png | 500px|left]]
 
[[Image:Excelente YQ Reflection.png | 500px|left]]
 
[[Image:Excelente Kiran Reflection.png | 500px|left]]
 
[[Image:Excelente Victor Reflection.png | 500px|left]]
 
[[Image:Excelente Wenguang Reflection.png | 500px|left]]
 
[[Image:Excelente Guohao Reflection.png | 500px|left]]
 
  
 
[[Image:Excelente Noelle2.png | 500px|left]]
 
[[Image:Excelente Noelle2.png | 500px|left]]

Revision as of 16:50, 19 April 2014

option

Home About Us Project Overview Project Management Project Documentation


Project Progress Summary

Deployed Site

Deployed Site Link: View Site
Deployed Mobile App (Google Play Store): View Site

Final Presentation Slides

Download our Final Slide Deck here!

Project Highlights

Changes in scope

Final Original
Excelente Current Scope.PNG Excelente Midterm Scope.PNG

Changes from Midterms

S/N Iteration Affected Area
Change
Rationale
0 0 Functionality & Requirements/Schedule Original Current <text>
1 8 ? ? ? ?
2 ? ? ? ? ?
3 ? ? ? ? ?
4 ? ? ? ? ?
5 ? ? ? ? ?
6 ? ? ? ? ?
7 ? ? ? ? ?
8 ? ? ? ? ?
9 ? ? ? ? ?

Project Achievements

Successfully completed

  • Evance Web App
  • Evance on Android
  • Evance on iOS

Successfully conducted

  • 3 User Tests
  • 3 External Validation Sessions
  • 2 Heuristics Evaluations
  • 1 Location Test
  • 1 Student Focus Group
  • 1 Proof of deployment

Project Management

Project Status

  • 100% Completed
  • All Core & Secondary functionalities completed

Project Schedule (Plan Vs Actual)

Excelente Schedule Final2.png




Excelente Manhour Final2.png

Project Metrics

Click to View the Latest Schedule and Bug Metrics

Technical Complexity

Excelente Complexity.gif

Quality of product

Intermediate Deliverable

Stage Specification Modules
Project Management Minutes Mentor minutes
Minutes Supervisor minutes
Minutes Internal minutes
Metrics Bug metrics
Metrics Schedule metrics
Analysis and Design Architecture Diagram Architecture diagram
ER Diagrams ER diagram
Use Case Diagram Use Case diagram
Use Case Diagram Mobile Workflow diagram
Market Survey/Analysis Survey/Analysis
Testing User Testing Heuristic evaluation
User Testing User test

Testing

Click to View the Test page

Reflection

Team Reflection

Stakeholder Management: Although our project is a self-proposed one, stakeholders are as important compared to sponsored projects. The team has learnt that managing expectations and requirements of stakeholders, especially when they differ drastically, is of paramount importance to the progress of the project.

Fail to Plan, Plan to Fail: The schedule, metrics, and all kinds of measurements are only tools to minimise impacts of setbacks or potential consequences. Even though any amount of planning is still insufficient to predict the realistic outcomes, the team has learnt that without a standard protocol to fall back on, it is difficult to ensure a steady progress flow.