|| Pushed to Sprint 7: Allow only users to cash out only at 50,000 credits which is equivalent to SGD$10. That will take approximately 17 days to reach 50,000 credits with the following breakdown.  
 
|| Pushed to Sprint 7: Allow only users to cash out only at 50,000 credits which is equivalent to SGD$10. That will take approximately 17 days to reach 50,000 credits with the following breakdown.  
  
Average credits that the user will earn from credits for impression: 50 credits.
+
Average credits that the user will earn from credits for impression: 50 credits. <br />
Average Number of squibs on the platform: 60 squibs
+
Average Number of squibs on the platform: 60 squibs <br />
Total credits that can be earned per day: 3000 credits
+
Total credits that can be earned per day: 3000 credits <br />
Average time to view total number of squibs on platform: 5 mins (+/-)
+
Average time to view total number of squibs on platform: 5 mins (+/-) <br />
Credits to reach 50,000 credits will take 17 days.  
+
Credits to reach 50,000 credits will take 17 days. <br />
 
|-
 
|-
  
Line 649: Line 649:
 
Following members going overseas:
 
Following members going overseas:
  
1. Agurz Gary: 6 - 22 Dec 13 (Denise covering till 13 Dec 13, Nicholas covering from 13 - 22 Dec 13)
+
1. Agurz Gary: 6 - 22 Dec 13 (Denise covering till 13 Dec 13, Nicholas covering from 13 - 22 Dec 13)<br />
2. Denise Wong: 14 - 21 Dec 13 (Agurz and Nicholas covering till 22 Dec 13)
+
2. Denise Wong: 14 - 21 Dec 13 (Agurz and Nicholas covering till 22 Dec 13)<br />
3. Janan Tan: 16 - 23 Dec 13 (Eleazar, Raf covering)
+
3. Janan Tan: 16 - 23 Dec 13 (Eleazar, Raf covering)<br />
4. Nicholas Li: 25 - 30 Dec 13 (Raf, Janan covering)
+
4. Nicholas Li: 25 - 30 Dec 13 (Raf, Janan covering)<br />
  
 
Changed the start date and end date of this current sprint.  
 
Changed the start date and end date of this current sprint.  

Revision as of 22:53, 26 February 2014

Agurz avatar.png
Denise avatar.png
Eleazar avatar.png
Dr.jeanlabs logo.jpg
Janan avatar.png
Nicholas avatar.png
Rafael avatar.png

HOME

 

DR.JEAN LABS

 

PROJECT OVERVIEW

 

PROJECT MANAGEMENT

 

PROJECT DOCUMENTATION

 


{ In a nutshell } { Acceptance Wiki } { MidTerm Wiki } { Final Wiki }


- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -


Project Management

Project Status:

We are currently XX% completion of our project. As a team, we are confident to complete the project by the end of IS480, Final Year Project term.

Stories Remaining
Story In Sprint Priority Circle Schedule
View Squib Tier 3 "Generate map" (User) 8 Scheduled
View Squib Tier 3 "Track User Location" (User) 8 Scheduled
Time period view of Squib Statistics 8 Scheduled
View Squib Tier 3 "Tag Squib location" (User) 8 Scheduled
View Squib Tier 3 "View nearby Squibs" (User) 8 Scheduled
Secured Login 8 Scheduled
Forgot Password 8 Scheduled
Search Function of Advertiser (Admin) 8 Scheduled
View Advertiser History (Admin) 8 Scheduled
Statistics for Admin 8 Scheduled
View Squib History (Admin) 8 Scheduled
FAQ 8 Scheduled

Project Schedule (Plan Vs Actual):

Iterations Planned Actual Comments
1 Brainstorm for ideas 10-Sep-13 10-Sep-13 Filtered out all the projects listed on the wiki and decided to do self-proposed project.
Submit Proposal for review 5-Oct-13 5-Oct-13 Decided to do with Sqkii project.
2 Low-Fidelity prototype 11-Oct-13 11-Oct-13 Developed paper prototype and conducted Heuristic Evaluation.
3 Dashboard (Admin) 18-Oct-13 18-Oct-13
Create new squib (Admin) 19-Oct-13 19-Oct-13
View Squib (Admin) 20-Oct-13 20-Oct-13
Delete Squib (Admin) 20-Oct-13 20-Oct-13
Approve Squib (Admin) 21-Oct-13 21-Oct-13
Create new Squib (Advertiser) 22-Oct-13 22-Oct-13
View Squib (Advertiser) 23-Oct-13 23-Oct-13
View Squib Tier 1 (User) 24-Oct-13 24-Oct-13
Project Management migrating over to SCRUM framework and using BurnChart to update and check the progress of the project.
4 Edit Squib (Advertiser) 8-Nov-13 Pushed to Sprint 6 in view of the closed beta launch on the 17 Feb 14.
Manage Payment (Admin) 8-Nov-13 Pushed to Sprint 7: Allow only users to cash out only at 50,000 credits which is equivalent to SGD$10. That will take approximately 17 days to reach 50,000 credits with the following breakdown.

Average credits that the user will earn from credits for impression: 50 credits.
Average Number of squibs on the platform: 60 squibs
Total credits that can be earned per day: 3000 credits
Average time to view total number of squibs on platform: 5 mins (+/-)
Credits to reach 50,000 credits will take 17 days.

Charge Account (Advertiser) 8-Nov-13 Pushed to Sprint 5. To focus all advertiser functions there.
Receive incentives (User) 8-Nov-13 Pushed to Sprint 7. Allow social media integration to work hand in hand for this to share the incentives earned on social media.
Edit Squib(Admin) 8-Nov-13 8-Nov-13
Edit Account(User) 9-Nov-14 9-Nov-13
Login 10-Nov-13 10-Nov-13
Logout 10-Nov-13 10-Nov-13
Create new Account (User) 10-Nov-13 10-Nov-13

This sprint span across exam period. Therefore there are lesser functions completed in this current sprint.

Changed the start date and end date of this current sprint.

5 Edit Squib(Advertiser) 7-Dec-13 8-Dec-13
Charge Account (Advertiser) 8-Dec-13 9-Dec-13 Integrated with application. Requires paypal email from the advertiser side to pay up using paypal. Delayed for one day due to the lack of immerse knowledge of implementing it.
Dashboard (Advertiser) 10-Dec-13 10-Dec-13
Save Squib (Advertiser) 11-Dec-13 13-Dec-13
View Notification (Advertiser) 13-Dec-13 Pushed to Sprint 6: In view of the current functions, we are unable unable to keep closely with the schedule, therefore to keep in schedule, we decided to push this function to next sprint.
View impression count (Advertiser) 13-Dec-13 13-Dec-13 Requested by the business requirement for basic statistic function for advertiser.
View user count and demo (Advertiser) 15-Dec-13 16-Dec-13 Requested by the business requirement for basic statistic function for advertiser.
Track revisited page (Advertiser) 16-Dec-13 16-Dec-13 Requested by the business requirement for basic statistic function for advertiser.
View overall statistical page (Advertiser) 17-Dec-13 17-Dec-13 Requested by the business requirement for basic statistic function for advertiser.
Create new account (Advertiser) 17-Dec-13 This function was removed. It was initiated by us as change agent in Dr. Jean Labs that Advertiser that wanted to get an account with us before the closed beta launch requires our validation of the company in order to start using the application.
View Account (Advertiser) 18-Dec-13 18-Dec-13
View History (Advertiser) 20-Dec-13 21-Dec-13 Shared by Rafael and Janan. Initial logic was to save squibs after viewed by 10 seconds in the history. However we identified that the swiping might lag and user might swipe across a few times. Therefore, we decided to save all squibs into history no matter what.
Contact Us (Advertiser) 21-Dec-13 20-Dec-13

Following members going overseas:

1. Agurz Gary: 6 - 22 Dec 13 (Denise covering till 13 Dec 13, Nicholas covering from 13 - 22 Dec 13)
2. Denise Wong: 14 - 21 Dec 13 (Agurz and Nicholas covering till 22 Dec 13)
3. Janan Tan: 16 - 23 Dec 13 (Eleazar, Raf covering)
4. Nicholas Li: 25 - 30 Dec 13 (Raf, Janan covering)

Changed the start date and end date of this current sprint.

In view of the closed beta launch which is in 17 Feb 14 (Sprint 6), we scrum all advertiser functions first in order for advertiser to be able to use the account before the closed beta launch and upload the squib to the platform.

At the same time, we are also conducting our UT 1 on the 27 - 29 Jan 14 (Sprint 6), we focus on advertiser functions for this current sprint.

6 Low-Fidelity prototype 11-Oct-13 11-Oct-13 Developed paper prototype and conducted Heuristic Evaluation.

Project Metrics:

Project Risks:

Technical Complexity:

Quality of the project

Intermediate Deliverables:

User Testing:

Quality of the project

Team Reflection:

Benjamin Gan Reflection: