===Project Schedule (Plan Vs Actual):===
 
===Project Schedule (Plan Vs Actual):===
 
{| border="1"
 
  
 
{| border="1"
 
{| border="1"
Line 392: Line 390:
 
|-
 
|-
  
|rowspan="2"| 1
+
|rowspan="4"| 1
 +
|| Brainstorm for ideas
 +
|| 1 Sept 2010
 +
||
 +
|| 25 Aug 2010
 +
|| Fiona took the Sales CRUD as well.
 +
|-
 +
 
 
|| Customer CRUD  
 
|| Customer CRUD  
 
|| 1 Sept 2010
 
|| 1 Sept 2010

Revision as of 20:02, 26 February 2014

Agurz avatar.png
Denise avatar.png
Eleazar avatar.png
Dr.jeanlabs logo.jpg
Janan avatar.png
Nicholas avatar.png
Rafael avatar.png

HOME

 

DR.JEAN LABS

 

PROJECT OVERVIEW

 

PROJECT MANAGEMENT

 

PROJECT DOCUMENTATION

 


{ In a nutshell } { Acceptance Wiki } { MidTerm Wiki } { Final Wiki }


- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -


Project Management

Project Status:

We are currently XX% completion of our project. As a team, we are confident to complete the project by the end of IS480, Final Year Project term.

Stories Remaining
Story In Sprint Priority Circle Schedule
View Squib Tier 3 "Generate map" (User) 8 Scheduled
View Squib Tier 3 "Track User Location" (User) 8 Scheduled
Time period view of Squib Statistics 8 Scheduled
View Squib Tier 3 "Tag Squib location" (User) 8 Scheduled
View Squib Tier 3 "View nearby Squibs" (User) 8 Scheduled
Secured Login 8 Scheduled
Forgot Password 8 Scheduled
Search Function of Advertiser (Admin) 8 Scheduled
View Advertiser History (Admin) 8 Scheduled
Statistics for Admin 8 Scheduled
View Squib History (Admin) 8 Scheduled
FAQ 8 Scheduled

Project Schedule (Plan Vs Actual):

Iterations Planned Actual Comments
1 Brainstorm for ideas 1 Sept 2010 25 Aug 2010 Fiona took the Sales CRUD as well.
Customer CRUD 1 Sept 2010 25 Aug 2010 Fiona took the Sales CRUD as well.

Project Metrics:

Project Risks:

Technical Complexity:

Quality of the project

Intermediate Deliverables:

User Testing:

Quality of the project

Team Reflection:

Benjamin Gan Reflection: