Difference between revisions of "IS480 Team wiki: 2013T1 ThunderBolt Project Management"
Jump to navigation
Jump to search
Line 52: | Line 52: | ||
'''Click here for our detailed schedule:''' [https://www.dropbox.com/s/natqomvruai2rrj/ThunderBolt%20Full%20Schedule.pdf]<br> | '''Click here for our detailed schedule:''' [https://www.dropbox.com/s/natqomvruai2rrj/ThunderBolt%20Full%20Schedule.pdf]<br> | ||
'''You may also refer to here for project status:''' [https://wiki.smu.edu.sg/is480/IS480_Team_wiki:_2013T1_ThunderBolt_Project_Overview_Scope#Project_Scope] | '''You may also refer to here for project status:''' [https://wiki.smu.edu.sg/is480/IS480_Team_wiki:_2013T1_ThunderBolt_Project_Overview_Scope#Project_Scope] | ||
+ | |||
+ | ===<div style="background: #d5a10d; padding: 15px; font-weight: bold; line-height: 0.3em"><font color= #FFFFFF>Project Status</font></div>=== | ||
===<div style="background: #d5a10d; padding: 15px; font-weight: bold; line-height: 0.3em"><font color= #FFFFFF>Planned VS Actual</font></div>=== | ===<div style="background: #d5a10d; padding: 15px; font-weight: bold; line-height: 0.3em"><font color= #FFFFFF>Planned VS Actual</font></div>=== |
Revision as of 23:59, 15 September 2013
About Us | Project Overview | Project Management | Project Documentation |
Project Schedule | Risks | Metrics | Resources and References | Learning Outcomes |
Project Schedule
Click here for our detailed schedule: [1]
You may also refer to here for project status: [2]
Project Status
Planned VS Actual
Iteration | Task Name | Reason for the delay/push back | Mitigation |
---|---|---|---|
1 | Single Sign On | Initially we tried to request a new app ID for SSO tool, however, the process was time consuming. Then we asked the creator (prof Benjamin Gan) of existing app ID for IS480 Scheduling to change the callback URL, unfortunately, the SSO admin tool was down and we have to wait for IITS to resolve it first before we can change the callback URL. | Hold the development for SSO and push the task to next iteration |
2 | Email notifications | Email notifications have been pushed back because the team feels that we should do notification when we complete edit and delete booking since these two functionality require the back-end to activate email system as well. | Pushed back to Iteration 4 |
4 | -Edit Schedule -Edit Booking |
The team underestimated the difficulty level of these two functionality, thus, we took longer time than expected to complete them | Took extra 2 days to complete them, the extra time was taken from buffer days we have |
5 | Manage Milestone Configuration | This back-end side of this functionality was more complex than expected | The owner of this task continue to work on it while others start new iteration to work on other functionality |