Line 179: | Line 179: | ||
[[Image:EV_Process.png|700px]] | [[Image:EV_Process.png|700px]] | ||
+ | |||
+ | <b>Step 2:</b> Android Application | ||
+ | |||
+ | - Bitmap region decoder | ||
+ | |||
+ | - Chosen panel becomes a zoomed in bitmap | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | <b>Solution:</b> | ||
+ | Modified codes to allow selection of rectangles | ||
====<div style=" border-bottom: 1px dotted; background: #FFFFFF; padding: 12px; font-weight: bold; line-height: 0.5em"><font color= black size = 4>Architecture Diagram</font></div>==== | ====<div style=" border-bottom: 1px dotted; background: #FFFFFF; padding: 12px; font-weight: bold; line-height: 0.5em"><font color= black size = 4>Architecture Diagram</font></div>==== |
Revision as of 08:53, 3 December 2013
Contents
Final Immediate Deliverables
FYP Marvel-lous Final Presentation
Link to Administrative Site
Link to download application
Project Summary
Iterations
Completed 9 Iterations
Milestones
Milestones completed:
1. Proposal
2. Acceptance
3. User Test 1
4. Mid-Term
5. Poster
6. User Test 2
Milestones in progress:
1. Final
Milestones (future):
1. Transfer of project to client
Note: Transfer of Project and Manual --> 6th December 2013 Training --> 6th December 2013
Functionalities
Total number of functions: 52
Number of completed functions: 52
Percentage of project completed: 100%
Deployment
Deployments:
- Website deployed to Google App Engine
- Android Application deployed to Google Play Store
Total number of deployments: 24
Type of deployment: White label
Project Highlights
Project Schedule
Timeline
Schedule Breakdown
Note: To view our Schedule, please click here.
Planned vs Actual
Note: This section only displays breakdown for delayed iterations. To view our Schedule Metric breakdown, please click here.
Project Metrics
Schedule Metric
Bug Metric
Reason for Iteration 8:
1. Payment
2. Enhanced viewing
Action plan:
1. Stop current iteration and fix bugs
2. Team members not part of Payment and Enhanced Viewing team continued with Iteration 9 functions
Reason for Iteration 9:
1. Payment (In-app billing)
Action plan:
1. Do not implement feedback for UT 2
2. Use buffer period
Project Risks
Risk Categories
Risk Management
Technical Complexity
Google Endpoints
The team has diffculties at 2 stages with Google End Points:
1. Connection from data store to the application
2. Connection from the application to data store.
Technical
Technical Complexity (Enhanced View Process)
Step 1: Panels are chosen for each image.
jQuery Plug in: Image area select
Issue:
- Aspect ratio
- Only able to choose square
Solution:
Modified codes to allow selection of rectangles
Step 2: Android Application
- Bitmap region decoder
- Chosen panel becomes a zoomed in bitmap
Solution:
Modified codes to allow selection of rectangles
Architecture Diagram
User Test 2
Intermediate Delivery
Stage | Document | Description |
---|---|---|
Project Management | Meeting Minutes | Iteration 1 to 9 - Internal, Supervisor & Client Meetings |
Project Metrics | Schedule and Bug Metric | |
Requirement Gathering | Market Research | Survey results and Research |
Analysis and Design | Diagrams | Use case diagram, ER diagram and Architecture Diagram |
Storyboard | Website | Website wire frames and screenshots |
Application | Application wire frames and screenshots | |
Testing | User Testing | User Testing 1 and 2 |
Submissions | Proposal | Proposal |
Acceptance | Acceptance presentation | |
Mid-Term | Mid-Term presentation |
Learning Outcome
Akash Gurung
Nur Hazirah
Priya Pathak
Roohiya Dudekula
Saloni Rawat
Saraniya Elengovan