Difference between revisions of "IS480 Team wiki: 2013T1 Marvel lous Final"
Line 86: | Line 86: | ||
− | [[Image: | + | [[Image:Marvel-LousFinalWikiScheduleMetric.png|700px]] |
+ | <b>Reason for major delay in Iteration 5 and 7:</b> | ||
− | + | - Google Endpoints | |
+ | |||
+ | - Iteration 5: Connection from data store to application | ||
+ | |||
+ | - Iteration 7: Connection from application to data store | ||
+ | |||
+ | |||
+ | <b>Action plan:</b> | ||
+ | |||
+ | - Did not drop any functionality | ||
+ | |||
+ | - Used up buffer days | ||
+ | |||
+ | |||
+ | <b>Reason for major delay in Iteration 8:</b> | ||
+ | |||
+ | - Payment | ||
+ | |||
+ | - Enhanced viewing | ||
+ | |||
+ | |||
+ | <b>Action plan:</b> | ||
+ | |||
+ | - Did not drop any functionality | ||
+ | |||
+ | - Rescheduled iteration by delaying iteration 8 | ||
+ | |||
+ | - Team not working on delayed functions moved ahead with Iteration 9 functions | ||
+ | |||
+ | |||
+ | <b>Reason for major delay in Iteration 9:</b> | ||
+ | |||
+ | - Payment (In-app billing) | ||
+ | |||
+ | |||
+ | <b>Action plan:</b> | ||
+ | |||
+ | - Did not drop any functionality | ||
+ | |||
+ | - Did not implement User Test 2 feedback | ||
+ | |||
+ | - Used UT 2 feedback implementation period to fix issue | ||
====<div style=" border-bottom: 1px dotted; background: #FFFFFF; padding: 12px; font-weight: bold; line-height: 0.5em"><font color= black size = 4>Bug Metric</font></div>==== | ====<div style=" border-bottom: 1px dotted; background: #FFFFFF; padding: 12px; font-weight: bold; line-height: 0.5em"><font color= black size = 4>Bug Metric</font></div>==== |
Revision as of 09:26, 3 December 2013
Contents
Final Immediate Deliverables
FYP Marvel-lous Final Presentation
Link to Administrative Site
Link to download application
Project Summary
Iterations
Completed 9 Iterations
Milestones
Milestones completed:
1. Proposal
2. Acceptance
3. User Test 1
4. Mid-Term
5. Poster
6. User Test 2
Milestones in progress:
1. Final
Milestones (future):
1. Transfer of project to client
Note: Transfer of Project and Manual --> 6th December 2013 Training --> 6th December 2013
Functionalities
Total number of functions: 52
Number of completed functions: 52
Percentage of project completed: 100%
Project Highlights
Project Schedule
Timeline
Schedule Breakdown
Note: To view our Schedule, please click here.
Planned vs Actual
Note: This section only displays breakdown for delayed iterations. To view our Schedule Metric breakdown, please click here.
Project Metrics
Schedule Metric
Reason for major delay in Iteration 5 and 7:
- Google Endpoints
- Iteration 5: Connection from data store to application
- Iteration 7: Connection from application to data store
Action plan:
- Did not drop any functionality
- Used up buffer days
Reason for major delay in Iteration 8:
- Payment
- Enhanced viewing
Action plan:
- Did not drop any functionality
- Rescheduled iteration by delaying iteration 8
- Team not working on delayed functions moved ahead with Iteration 9 functions
Reason for major delay in Iteration 9:
- Payment (In-app billing)
Action plan:
- Did not drop any functionality
- Did not implement User Test 2 feedback
- Used UT 2 feedback implementation period to fix issue
Bug Metric
Reason for Iteration 8:
1. Payment
2. Enhanced viewing
Action plan:
1. Stop current iteration and fix bugs
2. Team members not part of Payment and Enhanced Viewing team continued with Iteration 9 functions
Reason for Iteration 9:
1. Payment (In-app billing)
Action plan:
1. Do not implement feedback for UT 2
2. Use buffer period
Project Risks
Risk Categories
Risk Management
Technical
Technical Complexity (Enhanced View Process)
Step 1: Panels are chosen for each image.
jQuery Plug in: Image area select
Issue:
- Aspect ratio
- Only able to choose square
Solution:
Modified codes to allow selection of rectangles
Step 2: Android Application
- Bitmap region decoder
- Chosen panel becomes a zoomed in bitmap
Architecture Diagram
Deployment
Deployments:
- Website deployed to Google App Engine
- Android Application deployed to Google Play Store
Total number of deployments: 24
Type of deployment: White label
User Test 2
Intermediate Delivery
Stage | Document | Description |
---|---|---|
Project Management | Meeting Minutes | Iteration 1 to 9 - Internal, Supervisor & Client Meetings |
Project Metrics | Schedule and Bug Metric | |
Requirement Gathering | Market Research | Survey results and Research |
Analysis and Design | Diagrams | Use case diagram, ER diagram and Architecture Diagram |
Storyboard | Website | Website wire frames and screenshots |
Application | Application wire frames and screenshots | |
Testing | User Testing | User Testing 1 and 2 |
Submissions | Proposal | Proposal |
Acceptance | Acceptance presentation | |
Mid-Term | Mid-Term presentation |
Learning Outcome
Akash Gurung
Nur Hazirah
Priya Pathak
Roohiya Dudekula
Saloni Rawat
Saraniya Elengovan