Current Progress Overview
The coloured table below shows a visual representation on our project progress at a glance.
Our team has currently completed approximately 71.49% of development tasks.
The legend for colour shaded tasks are as follows:
- Green: Completed
- Yellow: To be completed in current Iteration 11
Percentage of Development Tasks Complete is calculated using Number of Completed Tasks (in Green) / Total Number of Tasks