HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2013T1 Kungfu Panda Project Management"

From IS480
Jump to navigation Jump to search
Line 35: Line 35:
 
The legend for colour shaded tasks are as follows:
 
The legend for colour shaded tasks are as follows:
 
<br/>- Green: Completed
 
<br/>- Green: Completed
<br/>- Yellow: To be completed in current Iteration 9
+
<br/>- Yellow: To be completed in current Iteration 11
<br/>- Orange: To be completed in the next Iteration 10
+
 
<br/>- Red: Later
 
 
<br/><br/>
 
<br/><br/>
 
Percentage of Development Tasks Complete is calculated using Number of Completed Tasks (in Green) / Total Number of Tasks
 
Percentage of Development Tasks Complete is calculated using Number of Completed Tasks (in Green) / Total Number of Tasks

Revision as of 13:05, 31 October 2013

KP-NewHeader.PNG
Home About Us Project Overview Project Management User Testing Project Documents


Project Progress Our Milestones Metrics Management Risk Assessment Changes


Current Progress Overview

The coloured table below shows a visual representation on our project progress at a glance.

Our team has currently completed approximately 63% of development tasks.

The legend for colour shaded tasks are as follows:
- Green: Completed
- Yellow: To be completed in current Iteration 11



Percentage of Development Tasks Complete is calculated using Number of Completed Tasks (in Green) / Total Number of Tasks