HeaderSIS.jpg

Difference between revisions of "IS480 Team wiki: 2013T1 Kungfu Panda Project Management"

From IS480
Jump to navigation Jump to search
Line 1: Line 1:
[[Image:KP-Header.PNG|950x400px|center]]
+
[[Image:KP-NewHeader.PNG|1000x500px|center]]
  
 
<div style="background-color:#FFFFFF" align="center">
 
<div style="background-color:#FFFFFF" align="center">

Revision as of 21:33, 30 October 2013

KP-NewHeader.PNG
Home About Us Project Overview Project Management User Testing Project Documents


Project Progress Our Milestones Metrics Management Risk Assessment Changes


Current Progress Overview

The coloured table below shows a visual representation on our project progress at a glance.

Our team has currently completed approximately 63% of development tasks.

The legend for colour shaded tasks are as follows:
- Green: Completed
- Yellow: To be completed in current Iteration 9
- Orange: To be completed in the next Iteration 10
- Red: Later

Percentage of Development Tasks Complete is calculated using Number of Completed Tasks (in Green) / Total Number of Tasks

933×467px
929×449px