Project Progress Summary

Final Presentation Slides Download!
Link to our Banch Teller Application: http://10.0.106.169:8080/SMUtBank_Teller/


Our team, Kungfu Panda, have been progressing well since the start of iteration 1; currently, we are in iteration 9 of our project. Although through the first half of the semester, we faced some changes requested by our client, our team faced them well. We were very focused. However, due to some last minute changes to our requirement, our team is currently rescheduling some task to the next iteration in order to complete the prioritized task first.

After Midterm, our team should have completed about 65% of the Branch Teller Application which includes the Party Customer, Deposit Account, Loan Account and Transaction use cases. We will be moving on to complete our X-Factor (Credit Approval and Teaching Tool) after our Midterm.

Project Highlights

  • Address feedbacks from our User Tests

Project Challenges

  • Had a hard time getting real Branch Teller from Banks to to do user test for us
  • Validation for the Credit Approval

Project Achievements

  • Complete the Application with all our client's requirement
  • Manage to secure one Branch Manager from a bank to try out our Application

Project Management

Project Status

Currently, our project is 100% completed.
Percentage of Development Tasks Complete = Number of Completed Tasks (in Green) / Total Number of Tasks

The below diagram shows a coloured diagram / map of development tasks that are completed and outstanding.
974×497px 1051×489px

Project Milestone

KP Milestone Table.PNG
KP FinalMilestone.PNG
Our Updated Project Schedule Download!

Project Schedule (Planned Vs Actual)

Project Metrics

Schedule Metrics

KP-ScheduleMetricsNew2.PNG



KP-Individule MetricsWk23.PNG



Below are some graphs which shows our schedule metrics for each iterations and for each individual members.
We have also calculated the average man hours per week each member put in.

KP-TeamScheduleMetricsWk23.PNG


KP-Individule MetricsGraphWk23.PNG


KP-ManhoursWk23.PNG



Bug Metrics

Total number of bugs encountered: 38
Bug Metric for FYP Week 22: 1 KP-GoodBugMetric.PNG
Below shown are the latest 25 bugs our team have encountered and is recorded in our Bug Tracker.
http://kfpbugtracker.no-ip.org/webissues

Bug tracker 101013.PNG



KP-BugMetricsNew2.PNG


KP-BugMFormula.PNG


KP Bug Metrics wk24a.PNG


KP Total Bug wk24b.PNG


KP Bug Score wk24c.PNG


KP-Midtermrisks.PNG

Technical Complexity

Frontend Complexity

KP-Frontend Complexity.PNG


Backend Complexity

Summary of Complexities Faced

  1. Data Integrity
    1. Ensured that insert statements made to the databases were ordered (serialized)
    2. Handled error flow should a transaction violation error occur
  2. Finance Formulas
    1. Had to research on finance formulas and understand the time value of money in order to complete this task
    2. Translated finance formulas (annuity formula) into Java code to be used in the Loan creation process
  3. Business Logic Errors
    1. Used XPath formulas within Tibco Designer to check for conditions such as insufficient balance or no such account and what to do subsequently
  4. Business Process Flow
    1. Entire business logic of the core banking systems is programmed inside the back-end services
    2. Deciding the order of events (which should come first etc.) in terms of business requirements was a key consideration in the design as well



Development using Tibco Enterprise Messaging Service (EMS)
Tibco Enterprise Messaging Service is a middleware product that implements the Java Messaging Service (JMS). Its flexible architecture helps simplify operational complexity by supporting the communication with a wide variety of technologies so that businesses can focus on the development and refinement of business requirements.

To develop on the EMS, our team had to use a sister product of Tibco, the Tibco Designer. This is a GUI-based developmental interface that allows developers to minimise coding whilst maintaining a high level of efficiency in capturing business process logic.

Sample Service: Account_Loan_Create Service KP-Account Loan Create.PNG


Quality of Application

Project Deliverables

Stage Specification Modules
Project Management Project Scope
Progress Overview
Risks
Metrics
Meeting Minutes
Design ER Diagram
General Architecture Diagram
Branch Teller Architecture Diagram
Testing UT 1 - Informal Testing
UT 2 - Deployment Exercise

Quality

Deployment

The following Branch Teller Functionalities have been deployed in the SMU tBank Server:
These represent 17 of 18 core functionalities.
- Party Create
- Party User PIN Create
- Party Read & Update
- Customer's Accounts Dashboard
- Account Deposit Read & Update
- Account Loan Create
- Manage Customer's Loan Accounts
- Account Loan Read & Update
- Transaction Deposit
- Transaction Withdrawal
- Transaction History Read
- Payment Credit Transfer Bill Payment
- Payment Loan Repayment Full
- Payment Loan Repayment Partial

The following Back End Services have been deployed in the SMU tBank Server:
These represent all 17 SMU Core Services.
- Party Customer Create
- Party Customer Read
- Party Customer Update
- Party Customer Read IC
- Account List Read
- Account Deposit Create
- Account Deposit Read
- Account Deposit Update
- Account Loan Create
- Account Loan Read
- Account Loan Update
- Transaction Deposit
- Transaction Withdrawal
- Transaction History Read
- Payment Credit Transfer Create
- Transaction FullLoanRepayment Create
- Payment Loan Repayment Partial

Testing

Client Testing

Deployment Exercise

User Test 1

User Test 2

Reflections

Team Reflection


Individual Reflections

Geraldine Koon (Project Manager)




Jonathan Ho (Business Analyst)



Zhu Juntao (Usability Engineer)




James Lim (Quality Assurance)




Kevin Ng (Lead Developer)




Tan Yao Guang (System Analyst)


KP-TeamPiclong.PNG


KP-SponsorComment.PNG