Line 182: | Line 182: | ||
The following shows the summary of our schedule metric thus far: | The following shows the summary of our schedule metric thus far: | ||
− | [[Image:Schedule metric mid.png | 600px]] | + | [[Image:Schedule metric mid.png | 600px | left]] |
− | + | {|Please refer to our Schedule metric calculation [[IS480_Team_wiki:_2012T2_Viaxeiros_Project_Management#Metrics | here]]. <br/> | |
+ | '''Highlights'''<br/> | ||
+ | In general, there is a delay in Iteration 3. This is due to having examinations during that period of time. Thus, despite the relatively less functions during that period of time, there is a slight delay in completing the schedule. Due to this, we have decided to increase the time period for the next iteration and also to allocate more tasks to be done then. | ||
+ | |} | ||
+ | <br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/><br/> | ||
'''Bug Metric''' | '''Bug Metric''' | ||
Revision as of 13:47, 25 February 2013
Welcome to Viaxeiros FYP Wiki Page
Mid Term Slides
|
Project Progress Summary
Progress
Currently, Viaxeiros in in their Iteration 9 on 26 February 2013, and in the midst of meeting the upcoming milestone, which is the Midterms presentation, at 26 February 2013. Currently, since the Acceptance Presentation which is at 5 November 2013, The following main features have been completed:
Based on the current status of the project, our team has decided to focus only on one of the additional functions proposed in the Acceptance Presentation, which is the Augmented Reality. |
Project Highlights
|
Project Management
Project Status
|
Project Schedule (Plan Vs Actual)
Key Changes
For more information on the schedule of our application, please click here. |
Project Metrics
Schedule Metric The following shows the summary of our schedule metric thus far: HighlightsIn general, there is a delay in Iteration 3. This is due to having examinations during that period of time. Thus, despite the relatively less functions during that period of time, there is a slight delay in completing the schedule. Due to this, we have decided to increase the time period for the next iteration and also to allocate more tasks to be done then.
Bug Count:
|
Project Risks
The following shows the top 3 list of risks that our team is currently facing. For more information of the other risks, please visit here:
|
Application Development
Intermediate Deliverables
|
Technical Complexity
|
Deployment
To download the application, you can visit this link to get the latest application in the Google Play Store. |
User Testing
|
Reflections
Learning Outcomes
|