Project Schedule & Milestones
Our project schedule is based on iterative process where we breakdown each iteration by subsets of requirements. Below is the detail of each iteration process.
- Iteration 0 - Getting Started
- Requirement Gathering
- Technology Research
- Scope and Stakeholder Confirmation
- Iteration 1 - CCA Website Part 1
- Login/Logout
- Create & Browse CCA Profile
- Post CCA Events/Announcements
- Iteration 2 - CCA Website Part 2
- Search CCA based on Keyword
- Join CCA
- Membership Confirmation + Notification
- Events Management
- Iteration 3 - CCA iPhone
- Browse CCA
- Join CCA
- iPhone Push Notification
- Events Management
- Iteration 4 - Facility Booking (iPhone + Backend)
- Backend Simulation of OASIS Facility Booking (Database + Web Service REST,JSON,XML)
- Browse Room
- Create Room Booking
- Confirm Room Booking
- Cancel Room Booking
- Backend Simulation of OASIS Facility Booking (Database + REST)
- Iteration 5 - WayFinder
- Map Design
- Display Maps
- Final Lap
- Overall Integration
- Implement UT Feedbacks
- Buffer time for identified issue